Bridge No. 37C0732 - E WILLIAM ST & COYOTE CREEK

Description: Bridge No. 37C0732 - E WILLIAM ST & COYOTE CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Clara County
City San Jose
Zip Code 95112
 
Senate District
13
Assembly District 23
Congressional District 16
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
San Jose Amy Olay (408) 975-3283   amy.olay@sanjoseca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$35 $6 $41
Non-bond Funding
State/Federal*
$360 $211 $571
Local**
$11 $21 $32
Private***
$0 $0 $0
 
Total**** $406 $238 $645

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$100 $183 $283 $255 $255 $28
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$306 $55 $362 $350 $350 $12
 
Total* $406 $238 $645 $605 $605 $39

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
02/13/2007 

08/31/2007 
 

 
02/13/2007 

08/31/2007 
100  07/03/2006 

08/31/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/04/2007 

03/31/2008 
 

10/15/2009 
09/04/2007 

04/10/2008 
100  09/01/2007 

04/10/2008 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2009 

12/31/2009 
10/15/2009 

10/15/2009 
07/21/2008 

10/31/2008 
100  07/21/2008 

10/31/2008 


Begin Closeout Phase

End Closeout Phase
06/30/2010 

 
 

 
06/30/2010 

 
100  12/30/2008 

 
18 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$35,170
Current Approved:
$35,170
Actual Expenditures:
$15,726

 

Status as of December 31, 2023.