Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 37C0732 - E WILLIAM ST & COYOTE CREEK |
Description: Bridge No. 37C0732 - E WILLIAM ST & COYOTE CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Clara County |
City | San Jose |
Zip Code | 95112 |
Senate District |
13 |
Assembly District | 23 |
Congressional District | 16 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
San Jose | Amy Olay | (408) 975-3283 | amy.olay@sanjoseca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$35 | $6 | $41 | ||||
Non-bond Funding | |||||||
State/Federal* |
$360 | $211 | $571 | ||||
Local** |
$11 | $21 | $32 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $406 | $238 | $645 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$100 | $183 | $283 | $255 | $255 | $28 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$306 | $55 | $362 | $350 | $350 | $12 | |
Total* | $406 | $238 | $645 | $605 | $605 | $39 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
02/13/2007 08/31/2007 |
|
02/13/2007 08/31/2007 |
100 | 07/03/2006 08/31/2007 |
7 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/04/2007 03/31/2008 |
10/15/2009 |
09/04/2007 04/10/2008 |
100 | 09/01/2007 04/10/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
06/01/2009 12/31/2009 |
10/15/2009 10/15/2009 |
07/21/2008 10/31/2008 |
100 | 07/21/2008 10/31/2008 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
06/30/2010 |
|
06/30/2010 |
100 | 12/30/2008 |
18 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$35,170 |
Current Approved: |
$35,170 |
Actual Expenditures: |
$15,726 |
Status as of December 31, 2023.