Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 38C0003 - SANTA FE AVENUE & TUOLUMNE RIVER |
Description: Bridge No. 38C0003 - SANTA FE AVENUE & TUOLUMNE RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Stanislaus County |
City | |
Zip Code | 95326 |
Senate District |
14 |
Assembly District | 25 |
Congressional District | 19 |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Stanislaus County | David Leamon | (209)525-4179 | leamond@stancounty.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$537 | $-73 | $464 | ||||
Non-bond Funding | |||||||
State/Federal* |
$4,143 | $13,499 | $17,643 | ||||
Local** |
$0 | $1,822 | $1,822 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $4,680 | $15,248 | $19,928 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $1,533 | $1,533 | $1,505 | $1,505 | $27 | |
Right of Way |
$0 | $150 | $150 | $29 | $29 | $121 | |
Construction |
$4,680 | $13,566 | $18,246 | $17,453 | $17,453 | $793 | |
Total* | $4,680 | $15,248 | $19,928 | $18,987 | $18,987 | $942 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
10/30/2001 07/30/2002 |
|
10/30/2001 07/30/2002 |
100 | 10/30/2001 07/30/2002 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/30/2001 06/30/2008 |
10/15/2009 |
04/30/2001 10/31/2013 |
100 | 06/08/2011 01/03/2017 |
-123 -39 |
Begin Right of Way Phase
End Right of Way Phase |
01/30/2008 01/30/2009 |
10/15/2009 |
01/30/2008 10/31/2013 |
100 | 06/01/2015 05/08/2017 |
-89 -43 |
Begin Construction Phase
End Construction Phase |
09/30/2010 08/11/2011 |
10/15/2009 10/15/2009 |
06/01/2013 06/30/2015 |
100 | 08/07/2017 05/30/2022 |
-51 -84 |
Begin Closeout Phase
End Closeout Phase |
06/30/2011 |
|
06/30/2011 |
50 | 05/30/2022 03/07/2023 |
-133 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$536,796 |
Current Approved: |
$463,732 |
Actual Expenditures: |
$463,732 |
Status as of December 31, 2023.