Caltrans Logo

Bridge No. 38C0003 - SANTA FE AVENUE & TUOLUMNE RIVER

Description: Bridge No. 38C0003 - SANTA FE AVENUE & TUOLUMNE RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus County
City
Zip Code 95326
 
Senate District
14
Assembly District 25
Congressional District 19
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Stanislaus County David Leamon (209)525-4179   leamond@stancounty.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$537 $-73 $464
Non-bond Funding
State/Federal*
$4,143 $13,499 $17,643
Local**
$0 $1,822 $1,822
Private***
$0 $0 $0
 
Total**** $4,680 $15,248 $19,928

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $1,533 $1,533 $1,505 $1,505 $27
Right of Way
$0 $150 $150 $29 $29 $121
Construction
$4,680 $13,566 $18,246 $17,453 $17,453 $793
 
Total* $4,680 $15,248 $19,928 $18,987 $18,987 $942

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
10/30/2001 

07/30/2002 
 

 
10/30/2001 

07/30/2002 
100  10/30/2001 

07/30/2002 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/30/2001 

06/30/2008 
 

10/15/2009 
04/30/2001 

10/31/2013 
100  06/08/2011 

01/03/2017 
-123 

-39 
Begin Right of Way Phase

End Right of Way Phase
01/30/2008 

01/30/2009 
 

10/15/2009 
01/30/2008 

10/31/2013 
100  06/01/2015 

05/08/2017 
-89 

-43 
Begin Construction Phase

End Construction Phase
09/30/2010 

08/11/2011 
10/15/2009 

10/15/2009 
06/01/2013 

06/30/2015 
100  08/07/2017 

05/30/2022 
-51 

-84 
Begin Closeout Phase

End Closeout Phase
06/30/2011 

 
 

 
06/30/2011 

 
50  05/30/2022 

03/07/2023 
-133 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$536,796
Current Approved:
$463,732
Actual Expenditures:
$463,732

 

Status as of December 31, 2023.