Bridge No. 38C0032 - MCHENRY AVENUE & STANISLAUS RIVER

Description: Bridge No. 38C0032 - MCHENRY AVENUE & STANISLAUS RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin County
City
Zip Code 95356
 
Senate District
14
Assembly District 26
Congressional District 11
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
San Joaquin County Michael Chung (209) 468-3586   mchung@sjgov.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$239 $0 $239
Non-bond Funding
State/Federal*
$2,033 $20,618 $22,651
Local**
$48 $3,006 $3,053
Private***
$0 $0 $0
 
Total**** $2,319 $23,624 $25,943

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$239 $3,468 $3,708 $2,611 $2,611 $1,097
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,080 $20,156 $22,236 $19,660 $19,660 $2,575
 
Total* $2,319 $23,624 $25,943 $22,271 $22,271 $3,673

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

02/14/1997 
 

 
 

02/14/1997 
100   

02/14/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/30/2007 

09/30/2010 
 

10/15/2009 
08/30/2007 

07/08/2011 
100  06/23/2008 

10/03/2016 
-10 

-64 
Begin Right of Way Phase

End Right of Way Phase
02/28/2008 

09/30/2010 
 

10/15/2009 
02/28/2008 

07/29/2011 
100  03/01/2014 

08/12/2016 
-73 

-61 
Begin Construction Phase

End Construction Phase
01/30/2011 

03/30/2013 
10/15/2009 

10/15/2009 
03/01/2012 

10/01/2014 
100  04/24/2017 

10/30/2020 
-63 

-74 
Begin Closeout Phase

End Closeout Phase
07/30/2013 

 
 

 
04/30/2015 

 
50  11/02/2020 

11/02/2022 
-67 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$238,576
Current Approved:
$238,576
Actual Expenditures:
$234,735

 

Status as of December 31, 2023.