Caltrans Logo

Bridge No. 38C0048 - GEER ROAD & TUOLUMNE RIVER

Description: Bridge No. 38C0048 - GEER ROAD & TUOLUMNE RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus County
City
Zip Code 95326
 
Senate District
14
Assembly District 25
Congressional District 19
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Stanislaus County David Leamon (209) 525-5703   leamond@stancounty.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$142 $0 $142
Non-bond Funding
State/Federal*
$1,093 $483 $1,577
Local**
$0 $0 $0
Private***
$0 $0 $0
 
Total**** $1,235 $483 $1,718

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $252 $252 $0 $0 $252
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,235 $231 $1,466 $1,235 $1,235 $231
 
Total* $1,235 $483 $1,718 $1,235 $1,235 $483

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
07/30/1997 

01/30/2001 
 

 
07/30/1997 

01/30/2001 
100  07/30/1997 

01/30/2001 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/30/2008 

01/30/2009 
 

10/15/2009 
01/30/2008 

03/31/2011 
100  03/01/2010 

12/31/2014 
-25 

-46 
Begin Right of Way Phase

End Right of Way Phase
04/30/2008 

04/30/2009 
 

 
04/30/2008 

04/30/2009 
100  04/30/2008 

04/30/2009 


Begin Construction Phase

End Construction Phase
05/30/2010 

 
10/15/2009 

10/15/2009 
07/01/2011 

07/31/2013 
100  07/01/2015 

11/17/2015 
-49 

-28 
Begin Closeout Phase

End Closeout Phase
09/30/2010 

 
 

 
09/30/2010 

 
100  01/31/2016 

10/23/2017 
-65 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$141,655
Current Approved:
$141,655
Actual Expenditures:
$141,655

 

Status as of December 31, 2023.