Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 38C0048 - GEER ROAD & TUOLUMNE RIVER |
Description: Bridge No. 38C0048 - GEER ROAD & TUOLUMNE RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Stanislaus County |
City | |
Zip Code | 95326 |
Senate District |
14 |
Assembly District | 25 |
Congressional District | 19 |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Stanislaus County | David Leamon | (209) 525-5703 | leamond@stancounty.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$142 | $0 | $142 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,093 | $483 | $1,577 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,235 | $483 | $1,718 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $252 | $252 | $0 | $0 | $252 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,235 | $231 | $1,466 | $1,235 | $1,235 | $231 | |
Total* | $1,235 | $483 | $1,718 | $1,235 | $1,235 | $483 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
07/30/1997 01/30/2001 |
|
07/30/1997 01/30/2001 |
100 | 07/30/1997 01/30/2001 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/30/2008 01/30/2009 |
10/15/2009 |
01/30/2008 03/31/2011 |
100 | 03/01/2010 12/31/2014 |
-25 -46 |
Begin Right of Way Phase
End Right of Way Phase |
04/30/2008 04/30/2009 |
|
04/30/2008 04/30/2009 |
100 | 04/30/2008 04/30/2009 |
0 0 |
Begin Construction Phase
End Construction Phase |
05/30/2010 |
10/15/2009 10/15/2009 |
07/01/2011 07/31/2013 |
100 | 07/01/2015 11/17/2015 |
-49 -28 |
Begin Closeout Phase
End Closeout Phase |
09/30/2010 |
|
09/30/2010 |
100 | 01/31/2016 10/23/2017 |
-65 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$141,655 |
Current Approved: |
$141,655 |
Actual Expenditures: |
$141,655 |
Status as of December 31, 2023.