Caltrans Logo

Bridge No. 38C0050 - CARPENTER ROAD & TUOLUMNE RIVER

Description: Bridge No. 38C0050 - CARPENTER ROAD & TUOLUMNE RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus County
City Modesto
Zip Code 95353
 
Senate District
12
Assembly District 26
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Modesto Vickey Dion (209) 571-5542   vdion@modestogov.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$1,591 $-403 $1,188
Non-bond Funding
State/Federal*
$12,682 $-2,787 $9,895
Local**
$100 $71 $171
Private***
$0 $0 $0
 
Total**** $14,373 $-3,119 $11,254

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$500 $297 $797 $724 $724 $73
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$13,873 $-3,417 $10,456 $10,123 $10,123 $333
 
Total* $14,373 $-3,119 $11,254 $10,848 $10,848 $406

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
11/30/1996 

03/30/1997 
 

 
11/30/1996 

03/30/1997 
100  01/01/1997 

01/01/1999 
-1 

-21 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/30/1997 

09/30/2008 
 

10/15/2009 
05/30/1997 

09/30/2010 
100  07/01/1997 

01/27/2012 
-1 

-16 
Begin Right of Way Phase

End Right of Way Phase
10/30/2008 

12/30/2008 
 

10/15/2009 
10/30/2008 

09/30/2010 
100  01/01/2010 

09/30/2010 
-14 

Begin Construction Phase

End Construction Phase
04/30/2009 

11/30/2009 
10/15/2009 

10/15/2009 
02/01/2011 

12/31/2011 
100  03/06/2012 

12/08/2015 
-13 

-48 
Begin Closeout Phase

End Closeout Phase
02/28/2010 

 
 

 
02/28/2010 

 
100  08/01/2016 

10/01/2019 
-78 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y

Bond Funding Cost
Adopted:
$1,591,233
Current Approved:
$1,187,855
Actual Expenditures:
$1,126,801

 

Status as of December 31, 2023.