Bridge No. 38C0050 - CARPENTER ROAD & TUOLUMNE RIVER |
Description: Bridge No. 38C0050 - CARPENTER ROAD & TUOLUMNE RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Stanislaus County |
City | Modesto |
Zip Code | 95353 |
Senate District |
12 |
Assembly District | 26 |
Congressional District | 18 |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Modesto | Vickey Dion | (209) 571-5542 | vdion@modestogov.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$1,591 | $-403 | $1,188 | ||||
Non-bond Funding | |||||||
State/Federal* |
$12,682 | $-2,787 | $9,895 | ||||
Local** |
$100 | $71 | $171 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $14,373 | $-3,119 | $11,254 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$500 | $297 | $797 | $724 | $724 | $73 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$13,873 | $-3,417 | $10,456 | $10,123 | $10,123 | $333 | |
Total* | $14,373 | $-3,119 | $11,254 | $10,848 | $10,848 | $406 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
11/30/1996 03/30/1997 |
|
11/30/1996 03/30/1997 |
100 | 01/01/1997 01/01/1999 |
-1 -21 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/30/1997 09/30/2008 |
10/15/2009 |
05/30/1997 09/30/2010 |
100 | 07/01/1997 01/27/2012 |
-1 -16 |
Begin Right of Way Phase
End Right of Way Phase |
10/30/2008 12/30/2008 |
10/15/2009 |
10/30/2008 09/30/2010 |
100 | 01/01/2010 09/30/2010 |
-14 0 |
Begin Construction Phase
End Construction Phase |
04/30/2009 11/30/2009 |
10/15/2009 10/15/2009 |
02/01/2011 12/31/2011 |
100 | 03/06/2012 12/08/2015 |
-13 -48 |
Begin Closeout Phase
End Closeout Phase |
02/28/2010 |
|
02/28/2010 |
100 | 08/01/2016 10/01/2019 |
-78 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$1,591,233 |
Current Approved: |
$1,187,855 |
Actual Expenditures: |
$1,126,801 |
Status as of December 31, 2023.