Caltrans Logo

Bridge No. 38C0202 - PETE MILLER ROAD & DELTA-MENDOTA CANAL

Description: Bridge No. 38C0202 - PETE MILLER ROAD & DELTA-MENDOTA CANAL - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus County
City
Zip Code 95322
 
Senate District
12
Assembly District 17
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Stanislaus County David Leamon 209-525-4151   leamond@stancounty.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$45 $47 $91
Non-bond Funding
State/Federal*
$345 $657 $1,003
Local**
$0 $0 $0
Private***
$0 $0 $0
 
Total**** $390 $704 $1,094

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $298 $298 $241 $0 $298
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$390 $406 $796 $744 $390 $406
 
Total* $390 $704 $1,094 $985 $390 $704

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

01/30/1999 
 

 
 

01/30/1999 
100  01/30/1998 

01/30/1999 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/30/2001 

01/30/2008 
 

10/15/2009 
01/30/2001 

04/28/2011 
100  04/01/2010 

10/01/2014 
-112 

-42 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/30/2009 

03/15/2011 
10/15/2009 

10/15/2009 
07/01/2011 

10/31/2011 
100  07/01/2015 

12/31/2015 
-49 

-51 
Begin Closeout Phase

End Closeout Phase
03/30/2010 

 
 

 
03/30/2010 

 
100  04/01/2016 

06/30/2016 
-73 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$44,733
Current Approved:
$91,288
Actual Expenditures:
$44,733

 

Status as of December 31, 2023.