Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 38C0202 - PETE MILLER ROAD & DELTA-MENDOTA CANAL |
Description: Bridge No. 38C0202 - PETE MILLER ROAD & DELTA-MENDOTA CANAL - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Stanislaus County |
City | |
Zip Code | 95322 |
Senate District |
12 |
Assembly District | 17 |
Congressional District | 18 |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Stanislaus County | David Leamon | 209-525-4151 | leamond@stancounty.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$45 | $47 | $91 | ||||
Non-bond Funding | |||||||
State/Federal* |
$345 | $657 | $1,003 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $390 | $704 | $1,094 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $298 | $298 | $241 | $0 | $298 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$390 | $406 | $796 | $744 | $390 | $406 | |
Total* | $390 | $704 | $1,094 | $985 | $390 | $704 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/30/1999 |
|
01/30/1999 |
100 | 01/30/1998 01/30/1999 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/30/2001 01/30/2008 |
10/15/2009 |
01/30/2001 04/28/2011 |
100 | 04/01/2010 10/01/2014 |
-112 -42 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/30/2009 03/15/2011 |
10/15/2009 10/15/2009 |
07/01/2011 10/31/2011 |
100 | 07/01/2015 12/31/2015 |
-49 -51 |
Begin Closeout Phase
End Closeout Phase |
03/30/2010 |
|
03/30/2010 |
100 | 04/01/2016 06/30/2016 |
-73 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$44,733 |
Current Approved: |
$91,288 |
Actual Expenditures: |
$44,733 |
Status as of December 31, 2023.