Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 39C0001 - RIVER ROAD & SAN JOAQUIN RIVER |
Description: Bridge No. 39C0001 - RIVER ROAD & SAN JOAQUIN RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Stanislaus County |
City | |
Zip Code | 95360 |
Senate District |
12 |
Assembly District | 17 |
Congressional District | 18 |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Stanislaus County | David Leamon | 209-525-5703 | leamond@stancounty.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$671 | $1,399 | $2,070 | ||||
Non-bond Funding | |||||||
State/Federal* |
$6,046 | $12,726 | $18,772 | ||||
Local** |
$112 | $250 | $362 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $6,829 | $14,375 | $21,204 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$964 | $2,192 | $3,156 | $3,315 | $3,337 | $-181 | |
Right of Way |
$14 | $262 | $276 | $52 | $276 | $0 | |
Construction |
$5,850 | $11,922 | $17,772 | $0 | $13,994 | $3,778 | |
Total* | $6,829 | $14,375 | $21,204 | $3,367 | $17,607 | $3,597 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
10/30/2002 05/30/2003 |
|
10/30/2002 05/30/2003 |
100 | 12/15/2011 11/15/2016 |
-111 -164 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/30/2008 08/30/2009 |
|
12/31/2020 03/31/2023 |
100 | 11/15/2016 06/30/2023 |
50 -3 |
Begin Right of Way Phase
End Right of Way Phase |
07/30/2009 12/30/2009 |
|
07/31/2022 12/31/2022 |
100 | 10/01/2021 06/30/2023 |
10 -6 |
Begin Construction Phase
End Construction Phase |
09/30/2011 02/28/2012 |
|
05/31/2023 03/31/2025 |
0 | 12/02/2024 12/01/2026 |
-18 -20 |
Begin Closeout Phase
End Closeout Phase |
|
|
05/31/2025 |
0 | 04/01/2027 04/03/2028 |
0 -35 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.