Bridge No. 39C0001 - RIVER ROAD & SAN JOAQUIN RIVER

Description: Bridge No. 39C0001 - RIVER ROAD & SAN JOAQUIN RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Stanislaus County
City
Zip Code 95360
 
Senate District
12
Assembly District 17
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Stanislaus County David Leamon 209-525-5703   leamond@stancounty.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$671 $1,399 $2,070
Non-bond Funding
State/Federal*
$6,046 $12,726 $18,772
Local**
$112 $250 $362
Private***
$0 $0 $0
 
Total**** $6,829 $14,375 $21,204

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$964 $2,192 $3,156 $3,315 $3,337 $-181
Right of Way
$14 $262 $276 $52 $276 $0
Construction
$5,850 $11,922 $17,772 $0 $13,994 $3,778
 
Total* $6,829 $14,375 $21,204 $3,367 $17,607 $3,597

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
10/30/2002 

05/30/2003 
 

 
10/30/2002 

05/30/2003 
100  12/15/2011 

11/15/2016 
-111 

-164 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/30/2008 

08/30/2009 
 

 
12/31/2020 

03/31/2023 
100  11/15/2016 

06/30/2023 
50 

-3 
Begin Right of Way Phase

End Right of Way Phase
07/30/2009 

12/30/2009 
 

 
07/31/2022 

12/31/2022 
100  10/01/2021 

06/30/2023 
10 

-6 
Begin Construction Phase

End Construction Phase
09/30/2011 

02/28/2012 
 

 
05/31/2023 

03/31/2025 
12/02/2024 

12/01/2026 
-18 

-20 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

05/31/2025 
04/01/2027 

04/03/2028 


-35 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.