Bridge No. 39C0314 - MERVEL AVE & CALIFORNIA AQUEDUCT

Description: Bridge No. 39C0314 - MERVEL AVE & CALIFORNIA AQUEDUCT - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Merced County
City
Zip Code 93635
 
Senate District
12
Assembly District 17
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Department of Water Resources Ray Miller (916) 653-9443   rhmiller@water.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$23 $0 $23
Non-bond Funding
State/Federal*
$353 $0 $353
Local**
$44 $0 $44
Private***
$0 $0 $0
 
Total**** $420 $0 $420

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$220 $0 $220 $75 $75 $145
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$200 $0 $200 $375 $375 $-175
 
Total* $420 $0 $420 $450 $450 $-30

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
08/26/2005 

04/01/2008 
 

 
08/26/2005 

04/01/2008 
100  08/26/2005 

09/01/2008 


-5 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/04/2007 

11/01/2008 
 

10/15/2009 
10/04/2007 

06/30/2010 
100  10/01/2010 

03/01/2013 
-36 

-32 
Begin Right of Way Phase

End Right of Way Phase
05/01/2008 

11/01/2008 
 

10/15/2009 
05/01/2008 

06/30/2010 
 

 


Begin Construction Phase

End Construction Phase
04/01/2009 

04/01/2010 
10/15/2009 

10/15/2009 
07/01/2010 

06/30/2011 
100  05/01/2014 

03/09/2015 
-47 

-45 
Begin Closeout Phase

End Closeout Phase
10/01/2010 

 
 

 
10/01/2010 

 
100  03/16/2017 

07/26/2018 
-79 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
$22,940
Current Approved:
$68,820
Actual Expenditures:
$50,037

 

Status as of December 31, 2023.