Bridge No. 39C0339 - CANAL SCHOOL ROAD & NEWMAN WASTEWAY |
Description: Bridge No. 39C0339 - CANAL SCHOOL ROAD & NEWMAN WASTEWAY - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Merced County |
City | |
Zip Code | 95340 |
Senate District |
12 |
Assembly District | 17 |
Congressional District | 18 |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Merced County | Randy Bardini | (209) 385-7601 | rbardini@co.merced.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$114 | $-114 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,005 | $-1,005 | $0 | ||||
Local** |
$36 | $-36 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,155 | $-1,155 | $0 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$160 | $-160 | $0 | $104 | $276 | $-276 | |
Right of Way |
$4 | $-4 | $0 | $0 | $0 | $0 | |
Construction |
$991 | $-991 | $0 | $0 | $1,432 | $-1,432 | |
Total* | $1,155 | $-1,155 | $0 | $104 | $1,708 | $-1,708 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/21/1997 06/13/2001 |
|
01/21/1997 06/13/2001 |
100 | 01/21/1997 06/13/2001 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/29/2001 03/01/2012 |
|
08/29/2001 03/01/2012 |
80 | 08/29/2001 03/01/2012 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/01/2011 04/01/2012 |
|
01/01/2011 04/01/2012 |
0 | 03/01/2011 04/01/2012 |
-2 0 |
Begin Construction Phase
End Construction Phase |
08/01/2012 01/30/2013 |
|
08/01/2012 01/30/2013 |
0 | 08/01/2012 01/30/2013 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
06/30/2013 |
|
06/30/2013 |
0 | 06/30/2013 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.