Bridge No. 42C0098 - S CALAVERAS AVE & LOS GATOS CREEK

Description: Bridge No. 42C0098 - S CALAVERAS AVE & LOS GATOS CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno County
City
Zip Code 93210
 
Senate District
16
Assembly District 30
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Fresno County Janet Dailey, P.E. (559) 600-4326   jdailey@co.fresno.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$46 $0 $46
Non-bond Funding
State/Federal*
$443 $-85 $357
Local**
$11 $0 $11
Private***
$0 $0 $0
 
Total**** $500 $-85 $415

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$100 $-21 $79 $161 $161 $-82
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$400 $-64 $336 $344 $344 $-8
 
Total* $500 $-85 $415 $505 $505 $-90

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/30/1995 

05/27/1997 
 

 
09/30/1995 

05/27/1997 
100  09/30/1995 

05/27/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/27/1997 

09/30/2010 
 

 
05/27/1997 

09/30/2010 
100  05/27/1997 

06/15/2010 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/30/2011 

03/30/2012 
 

 
09/30/2011 

03/30/2012 
100  08/25/2010 

04/25/2011 
13 

11 
Begin Closeout Phase

End Closeout Phase
09/30/2012 

 
 

 
09/30/2012 

 
50  04/26/2011 

06/19/2012 
17 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$45,880
Current Approved:
$45,880
Actual Expenditures:
$30,546

 

Status as of December 31, 2023.