Bridge No. 42C0098 - S CALAVERAS AVE & LOS GATOS CREEK |
Description: Bridge No. 42C0098 - S CALAVERAS AVE & LOS GATOS CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Fresno County |
City | |
Zip Code | 93210 |
Senate District |
16 |
Assembly District | 30 |
Congressional District | 20 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Fresno County | Janet Dailey, P.E. | (559) 600-4326 | jdailey@co.fresno.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$46 | $0 | $46 | ||||
Non-bond Funding | |||||||
State/Federal* |
$443 | $-85 | $357 | ||||
Local** |
$11 | $0 | $11 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $500 | $-85 | $415 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$100 | $-21 | $79 | $161 | $161 | $-82 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$400 | $-64 | $336 | $344 | $344 | $-8 | |
Total* | $500 | $-85 | $415 | $505 | $505 | $-90 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
09/30/1995 05/27/1997 |
|
09/30/1995 05/27/1997 |
100 | 09/30/1995 05/27/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/27/1997 09/30/2010 |
|
05/27/1997 09/30/2010 |
100 | 05/27/1997 06/15/2010 |
0 4 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2011 03/30/2012 |
|
09/30/2011 03/30/2012 |
100 | 08/25/2010 04/25/2011 |
13 11 |
Begin Closeout Phase
End Closeout Phase |
09/30/2012 |
|
09/30/2012 |
50 | 04/26/2011 06/19/2012 |
17 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$45,880 |
Current Approved: |
$45,880 |
Actual Expenditures: |
$30,546 |
Status as of December 31, 2023.