Bridge No. 42C0281 - W SIERRA AVE & DELTA-MENDOTA CANAL

Description: Bridge No. 42C0281 - W SIERRA AVE & DELTA-MENDOTA CANAL - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno County
City
Zip Code 93622
 
Senate District
16
Assembly District 31
Congressional District 19
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Fresno County Mohammad Alimi, P.E. (559) 600-4505   malimi@co.fresno.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$49 $-0 $49
Non-bond Funding
State/Federal*
$579 $-1 $578
Local**
$26 $0 $26
Private***
$0 $0 $0
 
Total**** $654 $-1 $653

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$230 $0 $230 $236 $236 $-6
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$424 $-1 $423 $458 $458 $-34
 
Total* $654 $-1 $653 $694 $694 $-41

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/30/2009 

10/01/2009 
04/30/2009 

08/11/2011 
04/30/2009 

10/01/2009 
100  04/30/2009 

08/11/2011 


-23 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2009 

09/28/2010 
11/01/2011 

09/16/2013 
01/01/2001 

09/28/2010 
100  11/01/2011 

09/16/2013 
-132 

-36 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/30/2011 

01/30/2012 
09/17/2013 

01/30/2014 
09/30/2011 

01/30/2012 
100  09/17/2013 

01/30/2014 
-24 

-24 
Begin Closeout Phase

End Closeout Phase
 

03/30/2013 
 

01/01/2015 
06/30/2012 

01/01/2015 
100  07/01/2014 

01/01/2015 
-24 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$48,633
Current Approved:
$48,568
Actual Expenditures:
$40,681

 

Status as of December 31, 2023.