Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 42C0281 - W SIERRA AVE & DELTA-MENDOTA CANAL |
Description: Bridge No. 42C0281 - W SIERRA AVE & DELTA-MENDOTA CANAL - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Fresno County |
City | |
Zip Code | 93622 |
Senate District |
16 |
Assembly District | 31 |
Congressional District | 19 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Fresno County | Mohammad Alimi, P.E. | (559) 600-4505 | malimi@co.fresno.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$49 | $-0 | $49 | ||||
Non-bond Funding | |||||||
State/Federal* |
$579 | $-1 | $578 | ||||
Local** |
$26 | $0 | $26 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $654 | $-1 | $653 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$230 | $0 | $230 | $236 | $236 | $-6 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$424 | $-1 | $423 | $458 | $458 | $-34 | |
Total* | $654 | $-1 | $653 | $694 | $694 | $-41 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
04/30/2009 10/01/2009 |
04/30/2009 08/11/2011 |
04/30/2009 10/01/2009 |
100 | 04/30/2009 08/11/2011 |
0 -23 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/01/2009 09/28/2010 |
11/01/2011 09/16/2013 |
01/01/2001 09/28/2010 |
100 | 11/01/2011 09/16/2013 |
-132 -36 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2011 01/30/2012 |
09/17/2013 01/30/2014 |
09/30/2011 01/30/2012 |
100 | 09/17/2013 01/30/2014 |
-24 -24 |
Begin Closeout Phase
End Closeout Phase |
03/30/2013 |
01/01/2015 |
06/30/2012 01/01/2015 |
100 | 07/01/2014 01/01/2015 |
-24 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$48,633 |
Current Approved: |
$48,568 |
Actual Expenditures: |
$40,681 |
Status as of December 31, 2023.