Bridge No. 43C0027 - PANOCHE ROAD & TRES PINOS CREEK

Description: Bridge No. 43C0027 - PANOCHE ROAD & TRES PINOS CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Benito County
City
Zip Code 95043
 
Senate District
12
Assembly District 28
Congressional District 17
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
San Benito County James Polfer (831) 636-4170   jpolfer@cosb.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$7 $0 $7
Non-bond Funding
State/Federal*
$77 $0 $77
Local**
$3 $0 $3
Private***
$0 $0 $0
 
Total**** $87 $0 $87

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$12 $0 $12 $0 $12 $0
Right of Way
$10 $0 $10 $0 $10 $0
Construction
$65 $0 $65 $0 $80 $-15
 
Total* $87 $0 $87 $0 $102 $-15

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

04/01/2009 
 

 
 

04/01/2009 
100  08/15/2008 

04/01/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/30/2009 

01/30/2010 
 

10/15/2009 
01/30/2009 

05/30/2012 
85  01/01/2011 

06/30/2017 
-23 

-62 
Begin Right of Way Phase

End Right of Way Phase
01/30/2010 

01/30/2011 
 

10/15/2009 
01/30/2010 

01/30/2013 
08/30/2016 

06/30/2017 
-80 

-54 
Begin Construction Phase

End Construction Phase
04/30/2011 

06/30/2012 
10/15/2009 

10/15/2009 
04/30/2013 

01/30/2014 
06/30/2017 

12/30/2017 
-51 

-48 
Begin Closeout Phase

End Closeout Phase
12/30/2012 

 
 

 
07/30/2014 

 
01/30/2018 

03/30/2018 
-43 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.