Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 43C0043 - LONE TREE RD & ARROYO DOS PICACHOS |
Description: Bridge No. 43C0043 - LONE TREE RD & ARROYO DOS PICACHOS - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Benito County |
City | Hollister |
Zip Code | 95023 |
Senate District |
12 |
Assembly District | 28 |
Congressional District | 17 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
San Benito County | Arman Nazemi | (831) 636-4170 | armann@cosb.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$195 | $-0 | $195 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,505 | $643 | $2,148 | ||||
Local** |
$1 | $116 | $117 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,701 | $759 | $2,460 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $331 | $331 | $331 | $331 | $0 | |
Right of Way |
$0 | $118 | $118 | $118 | $118 | $0 | |
Construction |
$1,701 | $310 | $2,011 | $2,009 | $2,009 | $2 | |
Total* | $1,701 | $759 | $2,460 | $2,458 | $2,458 | $2 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
08/25/1994 02/05/2002 |
|
08/25/1994 02/05/2002 |
100 | 08/25/1994 02/05/2002 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/05/2002 08/08/2005 |
|
02/05/2002 08/05/2005 |
100 | 02/05/2002 03/31/2007 |
0 -20 |
Begin Right of Way Phase
End Right of Way Phase |
01/05/2006 06/20/2006 |
|
01/05/2006 06/20/2006 |
100 | 02/01/2006 03/31/2007 |
0 -9 |
Begin Construction Phase
End Construction Phase |
05/30/2009 06/30/2010 |
|
08/20/2007 12/03/2008 |
100 | 08/20/2007 04/30/2009 |
0 -5 |
Begin Closeout Phase
End Closeout Phase |
12/30/2010 |
10/15/2009 |
03/01/2010 |
50 | 02/28/2011 03/15/2011 |
0 -13 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$194,990 |
Current Approved: |
$194,891 |
Actual Expenditures: |
$194,891 |
Status as of December 31, 2023.