Caltrans Logo

Bridge No. 43C0043 - LONE TREE RD & ARROYO DOS PICACHOS

Description: Bridge No. 43C0043 - LONE TREE RD & ARROYO DOS PICACHOS - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Benito County
City Hollister
Zip Code 95023
 
Senate District
12
Assembly District 28
Congressional District 17
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
San Benito County Arman Nazemi (831) 636-4170   armann@cosb.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$195 $-0 $195
Non-bond Funding
State/Federal*
$1,505 $643 $2,148
Local**
$1 $116 $117
Private***
$0 $0 $0
 
Total**** $1,701 $759 $2,460

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $331 $331 $331 $331 $0
Right of Way
$0 $118 $118 $118 $118 $0
Construction
$1,701 $310 $2,011 $2,009 $2,009 $2
 
Total* $1,701 $759 $2,460 $2,458 $2,458 $2

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
08/25/1994 

02/05/2002 
 

 
08/25/1994 

02/05/2002 
100  08/25/1994 

02/05/2002 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/05/2002 

08/08/2005 
 

 
02/05/2002 

08/05/2005 
100  02/05/2002 

03/31/2007 


-20 
Begin Right of Way Phase

End Right of Way Phase
01/05/2006 

06/20/2006 
 

 
01/05/2006 

06/20/2006 
100  02/01/2006 

03/31/2007 


-9 
Begin Construction Phase

End Construction Phase
05/30/2009 

06/30/2010 
 

 
08/20/2007 

12/03/2008 
100  08/20/2007 

04/30/2009 


-5 
Begin Closeout Phase

End Closeout Phase
 

12/30/2010 
 

10/15/2009 
 

03/01/2010 
50  02/28/2011 

03/15/2011 


-13 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$194,990
Current Approved:
$194,891
Actual Expenditures:
$194,891

 

Status as of December 31, 2023.