Bridge No. 44C0009 - NACIMIENTO LAKE DR & SAN ANTONIO RIVER |
Description: Bridge No. 44C0009 - NACIMIENTO LAKE DR & SAN ANTONIO RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Monterey County |
City | Bradley |
Zip Code | 93426 |
Senate District |
15 |
Assembly District | 28 |
Congressional District | 17 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Monterey County | Enrique Saavedra | (831) 755-4807 | Saavedraem@co.monterey.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$700 | $163 | $863 | ||||
Non-bond Funding | |||||||
State/Federal* |
$5,400 | $2,457 | $7,857 | ||||
Local** |
$0 | $155 | $155 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $6,100 | $2,775 | $8,875 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $1,350 | $1,350 | $2,801 | $2,801 | $-1,451 | |
Right of Way |
$100 | $405 | $505 | $711 | $711 | $-206 | |
Construction |
$6,000 | $1,020 | $7,020 | $7,173 | $7,173 | $-153 | |
Total* | $6,100 | $2,775 | $8,875 | $10,686 | $10,686 | $-1,810 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
02/02/1998 |
|
02/02/1998 |
100 | 10/03/1997 02/02/1998 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/30/2007 11/15/2008 |
10/15/2009 10/15/2009 |
10/30/2007 07/01/2010 |
100 | 10/30/2007 12/31/2018 |
0 -103 |
Begin Right of Way Phase
End Right of Way Phase |
01/01/2008 10/30/2008 |
10/15/2009 07/01/2015 |
01/01/2008 06/30/2016 |
100 | 03/01/2013 12/31/2018 |
-63 -30 |
Begin Construction Phase
End Construction Phase |
03/10/2010 |
|
07/01/2016 06/30/2019 |
99 | 02/05/2020 12/31/2024 |
-44 -67 |
Begin Closeout Phase
End Closeout Phase |
|
|
|
0 | 01/01/2025 06/30/2025 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.