Bridge No. 44C0009 - NACIMIENTO LAKE DR & SAN ANTONIO RIVER

Description: Bridge No. 44C0009 - NACIMIENTO LAKE DR & SAN ANTONIO RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Monterey County
City Bradley
Zip Code 93426
 
Senate District
15
Assembly District 28
Congressional District 17
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Monterey County Enrique Saavedra (831) 755-4807   Saavedraem@co.monterey.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$700 $163 $863
Non-bond Funding
State/Federal*
$5,400 $2,457 $7,857
Local**
$0 $155 $155
Private***
$0 $0 $0
 
Total**** $6,100 $2,775 $8,875

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $1,350 $1,350 $2,801 $2,801 $-1,451
Right of Way
$100 $405 $505 $711 $711 $-206
Construction
$6,000 $1,020 $7,020 $7,173 $7,173 $-153
 
Total* $6,100 $2,775 $8,875 $10,686 $10,686 $-1,810

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

02/02/1998 
 

 
 

02/02/1998 
100  10/03/1997 

02/02/1998 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/30/2007 

11/15/2008 
10/15/2009 

10/15/2009 
10/30/2007 

07/01/2010 
100  10/30/2007 

12/31/2018 


-103 
Begin Right of Way Phase

End Right of Way Phase
01/01/2008 

10/30/2008 
10/15/2009 

07/01/2015 
01/01/2008 

06/30/2016 
100  03/01/2013 

12/31/2018 
-63 

-30 
Begin Construction Phase

End Construction Phase
03/10/2010 

 
 

 
07/01/2016 

06/30/2019 
99  02/05/2020 

12/31/2024 
-44 

-67 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
01/01/2025 

06/30/2025 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.