Bridge No. 44C0059 - FIRST ST & SAN LORENZO CR |
Description: Bridge No. 44C0059 - FIRST ST & SAN LORENZO CR - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Monterey County |
City | King City |
Zip Code | 93930 |
Senate District |
12 |
Assembly District | 28 |
Congressional District | 17 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
King City | Michael Powers | 831-386-5917 | mpowers@kingcity.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$39 | $0 | $39 | ||||
Non-bond Funding | |||||||
State/Federal* |
$304 | $0 | $304 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $343 | $0 | $343 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$343 | $0 | $343 | $343 | $343 | $0 | |
Total* | $343 | $0 | $343 | $343 | $343 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
08/02/2001 |
|
08/02/2001 |
100 | 02/27/2001 02/03/2002 |
0 -6 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
02/04/2008 |
100 | 02/04/2002 02/04/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
04/30/2008 |
100 | 08/23/2006 04/30/2008 |
0 0 |
Begin Construction Phase
End Construction Phase |
07/01/2008 07/01/2010 |
|
05/01/2008 10/02/2009 |
100 | 05/01/2008 10/02/2009 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
07/01/2011 |
10/15/2009 |
07/01/2011 |
50 | 07/01/2011 12/01/2011 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.