Bridge No. 44C0099 - BORONDA RD & CARMEL RIVER |
Description: Bridge No. 44C0099 - BORONDA RD & CARMEL RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Monterey County |
City | Carmel Valley |
Zip Code | 93924 |
Senate District |
15 |
Assembly District | 27 |
Congressional District | 17 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Monterey County | Enrique Saavedra | (831) 755-4807 | saavedraem@co.monterey.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$127 | $-127 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$978 | $-978 | $0 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,105 | $-1,105 | $0 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $0 | $0 | $126 | $660 | $-660 | |
Right of Way |
$0 | $0 | $0 | $0 | $210 | $-210 | |
Construction |
$1,105 | $-1,105 | $0 | $0 | $4,430 | $-4,430 | |
Total* | $1,105 | $-1,105 | $0 | $126 | $5,300 | $-5,300 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
12/31/1997 |
|
12/31/1997 |
0 | 11/01/1997 01/28/1998 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/07/1998 06/15/2010 |
|
04/07/1998 06/15/2010 |
0 | 07/01/2010 12/31/2015 |
-149 -67 |
Begin Right of Way Phase
End Right of Way Phase |
06/15/2011 09/30/2012 |
|
06/15/2011 09/30/2012 |
0 | 12/31/2012 12/31/2015 |
-19 -40 |
Begin Construction Phase
End Construction Phase |
09/30/2013 01/01/2014 |
|
09/30/2013 01/01/2014 |
0 | 01/01/2016 01/01/2017 |
-27 -37 |
Begin Closeout Phase
End Closeout Phase |
06/01/2014 |
|
06/01/2014 |
0 | 01/01/2017 03/01/2017 |
-31 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.