Caltrans Logo

Bridge No. 44C0115 - SCHULTE RD & CARMEL RIVER

Description: Bridge No. 44C0115 - SCHULTE RD & CARMEL RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Monterey County
City Carmel Valley
Zip Code 93923
 
Senate District
15
Assembly District 27
Congressional District 17
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Monterey County Enrique Saavedra (831) 755-4807   saavedraem@co.monterey.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$367 $75 $442
Non-bond Funding
State/Federal*
$3,860 $1,146 $5,006
Local**
$251 $147 $399
Private***
$0 $0 $0
 
Total**** $4,478 $1,369 $5,847

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$1,228 $189 $1,417 $1,417 $1,417 $0
Right of Way
$50 $527 $577 $577 $577 $0
Construction
$3,200 $653 $3,853 $3,810 $3,810 $43
 
Total* $4,478 $1,369 $5,847 $5,803 $5,803 $43

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

01/30/1997 
 

 
 

01/30/1997 
100   

01/30/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/12/2003 

12/31/2007 
 

 
06/12/2003 

12/30/2010 
100  06/12/2003 

07/27/2009 


17 
Begin Right of Way Phase

End Right of Way Phase
05/17/2004 

12/31/2007 
 

10/15/2009 
05/17/2004 

04/30/2010 
100  05/17/2004 

06/30/2011 


-14 
Begin Construction Phase

End Construction Phase
09/30/2008 

06/30/2009 
10/15/2009 

10/15/2009 
04/30/2010 

04/30/2011 
100  07/21/2011 

12/31/2015 
-15 

-57 
Begin Closeout Phase

End Closeout Phase
12/30/2009 

 
 

 
12/30/2009 

09/06/2019 
100  01/01/2019 

09/06/2019 
-110 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$367,040
Current Approved:
$441,899
Actual Expenditures:
$398,791

 

Status as of December 31, 2023.