Bridge No. 44C0158 - LONOAK ROAD & LEWIS CREEK |
Description: Bridge No. 44C0158 - LONOAK ROAD & LEWIS CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Monterey County |
City | King City |
Zip Code | 95043 |
Senate District |
15 |
Assembly District | 28 |
Congressional District | 17 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Monterey County | Enrique Saavedra | (831) 755-4807 | saavedraem@co.monterey.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$338 | $-105 | $233 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,612 | $-55 | $2,557 | ||||
Local** |
$0 | $418 | $418 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $2,950 | $258 | $3,208 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $521 | $521 | $535 | $535 | $-14 | |
Right of Way |
$0 | $264 | $264 | $264 | $264 | $0 | |
Construction |
$2,950 | $-527 | $2,423 | $2,278 | $2,278 | $145 | |
Total* | $2,950 | $258 | $3,208 | $3,077 | $3,077 | $131 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
08/07/1998 |
|
08/07/1998 |
100 | 11/19/1997 09/16/1998 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/12/2003 01/30/2008 |
|
06/12/2003 07/10/2009 |
100 | 06/12/2003 07/27/2009 |
0 -1 |
Begin Right of Way Phase
End Right of Way Phase |
09/15/2004 01/30/2008 |
10/15/2009 |
09/15/2004 12/31/2009 |
100 | 07/01/2009 12/15/2010 |
-58 -12 |
Begin Construction Phase
End Construction Phase |
04/15/2009 01/15/2010 |
10/15/2009 |
04/01/2011 12/31/2011 |
100 | 05/02/2011 07/22/2014 |
-1 -31 |
Begin Closeout Phase
End Closeout Phase |
01/15/2010 |
10/15/2009 |
01/15/2010 |
0 | 07/23/2014 08/05/2014 |
-55 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$338,365 |
Current Approved: |
$233,249 |
Actual Expenditures: |
$233,249 |
Status as of December 31, 2023.