Caltrans Logo

Bridge No. 46C0027 - AVENUE 416 & KINGS RIVER

Description: Bridge No. 46C0027 - AVENUE 416 & KINGS RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare County
City
Zip Code 93654
 
Senate District
16
Assembly District 31
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Tulare County Hernan Beltran (559) 624-7176   HBeltran@co.tulare.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$522 $-23 $499
Non-bond Funding
State/Federal*
$4,028 $11,837 $15,865
Local**
$0 $1,827 $1,827
Private***
$0 $0 $0
 
Total**** $4,550 $13,641 $18,191

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $1,770 $1,770 $1,770 $1,770 $0
Right of Way
$0 $417 $417 $417 $417 $0
Construction
$4,550 $11,453 $16,003 $16,003 $16,003 $0
 
Total* $4,550 $13,641 $18,191 $18,191 $18,191 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
01/09/2002 

06/30/2008 
 

 
01/09/2002 

06/30/2008 
100  01/09/2002 

06/30/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2008 

12/31/2011 
 

10/15/2009 
07/01/2008 

12/31/2010 
100  12/22/2009 

03/01/2012 
-18 

-14 
Begin Right of Way Phase

End Right of Way Phase
07/01/2008 

12/31/2011 
 

10/15/2009 
07/01/2008 

10/31/2010 
100  04/01/2010 

07/31/2012 
-21 

-21 
Begin Construction Phase

End Construction Phase
03/01/2012 

12/30/2014 
10/15/2009 

10/15/2009 
11/01/2010 

12/31/2012 
100  08/28/2012 

03/31/2015 
-22 

-27 
Begin Closeout Phase

End Closeout Phase
06/30/2015 

 
10/15/2009 

 
06/30/2013 

 
100  04/01/2015 

01/28/2019 
-21 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$521,885
Current Approved:
$498,711
Actual Expenditures:
$498,711

 

Status as of December 31, 2023.