Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 46C0027 - AVENUE 416 & KINGS RIVER |
Description: Bridge No. 46C0027 - AVENUE 416 & KINGS RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Tulare County |
City | |
Zip Code | 93654 |
Senate District |
16 |
Assembly District | 31 |
Congressional District | 21 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Tulare County | Hernan Beltran | (559) 624-7176 | HBeltran@co.tulare.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$522 | $-23 | $499 | ||||
Non-bond Funding | |||||||
State/Federal* |
$4,028 | $11,837 | $15,865 | ||||
Local** |
$0 | $1,827 | $1,827 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $4,550 | $13,641 | $18,191 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $1,770 | $1,770 | $1,770 | $1,770 | $0 | |
Right of Way |
$0 | $417 | $417 | $417 | $417 | $0 | |
Construction |
$4,550 | $11,453 | $16,003 | $16,003 | $16,003 | $0 | |
Total* | $4,550 | $13,641 | $18,191 | $18,191 | $18,191 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/09/2002 06/30/2008 |
|
01/09/2002 06/30/2008 |
100 | 01/09/2002 06/30/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2008 12/31/2011 |
10/15/2009 |
07/01/2008 12/31/2010 |
100 | 12/22/2009 03/01/2012 |
-18 -14 |
Begin Right of Way Phase
End Right of Way Phase |
07/01/2008 12/31/2011 |
10/15/2009 |
07/01/2008 10/31/2010 |
100 | 04/01/2010 07/31/2012 |
-21 -21 |
Begin Construction Phase
End Construction Phase |
03/01/2012 12/30/2014 |
10/15/2009 10/15/2009 |
11/01/2010 12/31/2012 |
100 | 08/28/2012 03/31/2015 |
-22 -27 |
Begin Closeout Phase
End Closeout Phase |
06/30/2015 |
10/15/2009 |
06/30/2013 |
100 | 04/01/2015 01/28/2019 |
-21 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$521,885 |
Current Approved: |
$498,711 |
Actual Expenditures: |
$498,711 |
Status as of December 31, 2023.