Caltrans Logo

Bridge No. 49C0338 - MOONSTONE BEACH & LEFFINGWELL CREEK

Description: Bridge No. 49C0338 - MOONSTONE BEACH & LEFFINGWELL CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Luis Obispo County
City Cambria
Zip Code 93408, 93428
 
Senate District
15
Assembly District 33
Congressional District 23
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
San Luis Obispo County Dave Flynn (805) 781-4463   dflynn@co.slo.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$69 $0 $69
Non-bond Funding
State/Federal*
$5,473 $-943 $4,530
Local**
$665 $-69 $596
Private***
$0 $0 $0
 
Total**** $6,206 $-1,011 $5,195

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$825 $0 $825 $1,000 $1,000 $-175
Right of Way
$16 $0 $16 $36 $36 $-20
Construction
$5,365 $-1,011 $4,354 $4,543 $4,543 $-189
 
Total* $6,206 $-1,011 $5,195 $5,580 $5,580 $-385

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
02/01/1997 

02/28/1997 
 

 
02/01/1997 

02/28/1997 
100  02/01/1997 

02/28/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/30/2003 

01/30/2008 
 

 
09/30/2003 

04/07/2008 
100  10/20/2003 

04/07/2008 
-1 

Begin Right of Way Phase

End Right of Way Phase
10/22/2007 

03/17/2008 
 

 
10/22/2007 

03/17/2008 
100  10/22/2007 

03/17/2008 


Begin Construction Phase

End Construction Phase
06/30/2008 

06/30/2009 
 

 
04/14/2008 

07/31/2009 
100  07/14/2008 

08/21/2009 
-3 

-1 
Begin Closeout Phase

End Closeout Phase
01/30/2010 

 
10/15/2009 

 
01/30/2010 

 
100  06/30/2010 

11/17/2010 
-5 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$68,820
Current Approved:
$68,820
Actual Expenditures:
$68,034

 

Status as of December 31, 2023.