Bridge No. 49C0338 - MOONSTONE BEACH & LEFFINGWELL CREEK |
Description: Bridge No. 49C0338 - MOONSTONE BEACH & LEFFINGWELL CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Luis Obispo County |
City | Cambria |
Zip Code | 93408, 93428 |
Senate District |
15 |
Assembly District | 33 |
Congressional District | 23 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
San Luis Obispo County | Dave Flynn | (805) 781-4463 | dflynn@co.slo.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$69 | $0 | $69 | ||||
Non-bond Funding | |||||||
State/Federal* |
$5,473 | $-943 | $4,530 | ||||
Local** |
$665 | $-69 | $596 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $6,206 | $-1,011 | $5,195 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$825 | $0 | $825 | $1,000 | $1,000 | $-175 | |
Right of Way |
$16 | $0 | $16 | $36 | $36 | $-20 | |
Construction |
$5,365 | $-1,011 | $4,354 | $4,543 | $4,543 | $-189 | |
Total* | $6,206 | $-1,011 | $5,195 | $5,580 | $5,580 | $-385 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
02/01/1997 02/28/1997 |
|
02/01/1997 02/28/1997 |
100 | 02/01/1997 02/28/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/30/2003 01/30/2008 |
|
09/30/2003 04/07/2008 |
100 | 10/20/2003 04/07/2008 |
-1 0 |
Begin Right of Way Phase
End Right of Way Phase |
10/22/2007 03/17/2008 |
|
10/22/2007 03/17/2008 |
100 | 10/22/2007 03/17/2008 |
0 0 |
Begin Construction Phase
End Construction Phase |
06/30/2008 06/30/2009 |
|
04/14/2008 07/31/2009 |
100 | 07/14/2008 08/21/2009 |
-3 -1 |
Begin Closeout Phase
End Closeout Phase |
01/30/2010 |
10/15/2009 |
01/30/2010 |
100 | 06/30/2010 11/17/2010 |
-5 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$68,820 |
Current Approved: |
$68,820 |
Actual Expenditures: |
$68,034 |
Status as of December 31, 2023.