Bridge No. 50C0021L - MANOR ST SB & KERN RIVER

Description: Bridge No. 50C0021L - MANOR ST SB & KERN RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern County
City Bakersfield
Zip Code 93308
 
Senate District
18
Assembly District 32
Congressional District 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Bakersfield Navdip Grewal (661) 326-3361   ngrewal@bakersfieldcity.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$298 $-238 $60
Non-bond Funding
State/Federal*
$2,302 $8,097 $10,399
Local**
$0 $1,287 $1,287
Private***
$0 $0 $0
 
Total**** $2,600 $9,146 $11,746

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $1,466 $1,466 $908 $908 $558
Right of Way
$0 $0 $0 $23 $23 $-23
Construction
$2,600 $7,680 $10,280 $10,279 $10,279 $1
 
Total* $2,600 $9,146 $11,746 $11,209 $11,209 $537

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

08/12/1998 
 

 
 

08/12/1998 
100   

11/04/2015 


-210 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/10/1996 

06/30/2010 
10/15/2009 

10/15/2009 
06/10/1996 

06/30/2010 
100  11/05/2015 

09/29/2017 
-236 

-88 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100  04/01/2017 

10/01/2017 


Begin Construction Phase

End Construction Phase
07/01/2010 

07/01/2011 
10/15/2009 

10/15/2009 
07/01/2010 

07/01/2011 
100  12/02/2019 

04/14/2023 
-115 

-143 
Begin Closeout Phase

End Closeout Phase
10/30/2011 

 
 

 
10/30/2011 

 
50  01/01/2024 

12/31/2024 
-148 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$298,220
Current Approved:
$30,052
Actual Expenditures:
$30,052

 

Status as of December 31, 2023.