Bridge No. 50C0021R - MANOR ST NB & KERN RIVER |
Description: Bridge No. 50C0021R - MANOR ST NB & KERN RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Kern County |
City | Bakersfield |
Zip Code | 93308 |
Senate District |
18 |
Assembly District | 32 |
Congressional District | 22 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Bakersfield | Navdip Grewal | (661) 326-3361 | ngrewal@bakersfieldcity.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$298 | $-298 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,302 | $-2,302 | $0 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $2,600 | $-2,600 | $0 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$2,600 | $-2,600 | $0 | $0 | $0 | $0 | |
Total* | $2,600 | $-2,600 | $0 | $0 | $0 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
08/12/1998 |
|
08/12/1998 |
100 | 11/04/2015 |
0 -210 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/10/1996 06/30/2010 |
10/15/2009 10/15/2009 |
06/10/1996 06/30/2010 |
100 | 11/05/2015 09/29/2017 |
-236 -88 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | 04/01/2017 10/01/2017 |
0 0 |
Begin Construction Phase
End Construction Phase |
07/01/2010 07/01/2011 |
10/15/2009 10/15/2009 |
07/01/2010 07/01/2011 |
100 | 12/02/2019 04/14/2023 |
-115 -143 |
Begin Closeout Phase
End Closeout Phase |
10/30/2011 |
|
10/30/2011 |
50 | 01/01/2024 12/31/2024 |
-148 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$298,220 |
Current Approved: |
$30,051 |
Actual Expenditures: |
$30,051 |
Status as of December 31, 2023.