Caltrans Logo

Bridge No. 51C0002 - SAN MARCOS RD & MARIA YGNACIA CREEK

Description: Bridge No. 51C0002 - SAN MARCOS RD & MARIA YGNACIA CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara County
City
Zip Code 93111
 
Senate District
19
Assembly District 35
Congressional District 23
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Santa Barbara County Chris Sneddon (805) 568-3005   csneddo@cosbpw.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$88 $22 $110
Non-bond Funding
State/Federal*
$800 $407 $1,207
Local**
$16 $31 $47
Private***
$0 $0 $0
 
Total**** $904 $460 $1,364

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$137 $269 $406 $406 $406 $0
Right of Way
$0 $0 $0 $6 $6 $-6
Construction
$767 $191 $958 $958 $958 $0
 
Total* $904 $460 $1,364 $1,370 $1,370 $-6

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
01/30/2008 

03/30/2008 
 

 
01/30/2008 

03/30/2008 
100  01/30/2008 

03/30/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/30/2008 

09/30/2008 
10/15/2009 

10/15/2009 
03/30/2008 

05/15/2010 
100  03/30/2008 

09/30/2011 


-17 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

10/15/2009 
 

05/15/2010 
100  06/15/2010 

05/31/2011 


-13 
Begin Construction Phase

End Construction Phase
11/30/2008 

03/30/2009 
10/15/2009 

10/15/2009 
09/15/2010 

01/15/2011 
100  10/01/2011 

05/30/2012 
-13 

-17 
Begin Closeout Phase

End Closeout Phase
09/30/2009 

 
10/15/2009 

 
06/15/2011 

 
50  05/31/2012 

06/13/2013 
-12 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$87,953
Current Approved:
$109,874
Actual Expenditures:
$109,874

 

Status as of December 31, 2023.