Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 51C0002 - SAN MARCOS RD & MARIA YGNACIA CREEK |
Description: Bridge No. 51C0002 - SAN MARCOS RD & MARIA YGNACIA CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Barbara County |
City | |
Zip Code | 93111 |
Senate District |
19 |
Assembly District | 35 |
Congressional District | 23 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Santa Barbara County | Chris Sneddon | (805) 568-3005 | csneddo@cosbpw.net |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$88 | $22 | $110 | ||||
Non-bond Funding | |||||||
State/Federal* |
$800 | $407 | $1,207 | ||||
Local** |
$16 | $31 | $47 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $904 | $460 | $1,364 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$137 | $269 | $406 | $406 | $406 | $0 | |
Right of Way |
$0 | $0 | $0 | $6 | $6 | $-6 | |
Construction |
$767 | $191 | $958 | $958 | $958 | $0 | |
Total* | $904 | $460 | $1,364 | $1,370 | $1,370 | $-6 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/30/2008 03/30/2008 |
|
01/30/2008 03/30/2008 |
100 | 01/30/2008 03/30/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/30/2008 09/30/2008 |
10/15/2009 10/15/2009 |
03/30/2008 05/15/2010 |
100 | 03/30/2008 09/30/2011 |
0 -17 |
Begin Right of Way Phase
End Right of Way Phase |
|
10/15/2009 |
05/15/2010 |
100 | 06/15/2010 05/31/2011 |
0 -13 |
Begin Construction Phase
End Construction Phase |
11/30/2008 03/30/2009 |
10/15/2009 10/15/2009 |
09/15/2010 01/15/2011 |
100 | 10/01/2011 05/30/2012 |
-13 -17 |
Begin Closeout Phase
End Closeout Phase |
09/30/2009 |
10/15/2009 |
06/15/2011 |
50 | 05/31/2012 06/13/2013 |
-12 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$87,953 |
Current Approved: |
$109,874 |
Actual Expenditures: |
$109,874 |
Status as of December 31, 2023.