Caltrans Logo

Bridge No. 51C0006 - FLORADALE AVE & SANTA YNEZ RIVER

Description: Bridge No. 51C0006 - FLORADALE AVE & SANTA YNEZ RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Santa Barbara County
City
Zip Code 93436
 
Senate District
19
Assembly District 33
Congressional District 24
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Santa Barbara County Chris Sneddon (805) 568-3005   csneddo@cosbpw.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$1,273 $-632 $641
Non-bond Funding
State/Federal*
$10,686 $8,921 $19,607
Local**
$214 $1,966 $2,180
Private***
$0 $0 $0
 
Total**** $12,174 $10,255 $22,428

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$1,072 $1,847 $2,918 $2,658 $2,740 $179
Right of Way
$260 $0 $260 $205 $205 $55
Construction
$10,842 $8,408 $19,250 $15,814 $19,250 $0
 
Total* $12,174 $10,255 $22,428 $18,676 $22,194 $234

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

03/30/1997 
 

 
 

03/30/1997 
100   

03/30/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/30/1999 

06/30/2009 
 

 
04/30/1999 

08/15/2020 
100  04/30/1999 

04/01/2021 


-8 
Begin Right of Way Phase

End Right of Way Phase
07/30/2009 

06/30/2010 
 

 
07/13/2015 

06/30/2020 
100  11/30/2017 

12/31/2022 
-29 

-30 
Begin Construction Phase

End Construction Phase
07/30/2010 

01/30/2012 
 

 
08/31/2020 

07/31/2025 
95  11/15/2020 

12/21/2025 
-3 

-5 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

07/31/2026 
12/31/2025 

12/31/2026 


-5 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.