Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 51C0006 - FLORADALE AVE & SANTA YNEZ RIVER |
Description: Bridge No. 51C0006 - FLORADALE AVE & SANTA YNEZ RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Santa Barbara County |
City | |
Zip Code | 93436 |
Senate District |
19 |
Assembly District | 33 |
Congressional District | 24 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Santa Barbara County | Chris Sneddon | (805) 568-3005 | csneddo@cosbpw.net |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$1,273 | $-632 | $641 | ||||
Non-bond Funding | |||||||
State/Federal* |
$10,686 | $8,921 | $19,607 | ||||
Local** |
$214 | $1,966 | $2,180 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $12,174 | $10,255 | $22,428 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$1,072 | $1,847 | $2,918 | $2,658 | $2,740 | $179 | |
Right of Way |
$260 | $0 | $260 | $205 | $205 | $55 | |
Construction |
$10,842 | $8,408 | $19,250 | $15,814 | $19,250 | $0 | |
Total* | $12,174 | $10,255 | $22,428 | $18,676 | $22,194 | $234 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
03/30/1997 |
|
03/30/1997 |
100 | 03/30/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/30/1999 06/30/2009 |
|
04/30/1999 08/15/2020 |
100 | 04/30/1999 04/01/2021 |
0 -8 |
Begin Right of Way Phase
End Right of Way Phase |
07/30/2009 06/30/2010 |
|
07/13/2015 06/30/2020 |
100 | 11/30/2017 12/31/2022 |
-29 -30 |
Begin Construction Phase
End Construction Phase |
07/30/2010 01/30/2012 |
|
08/31/2020 07/31/2025 |
95 | 11/15/2020 12/21/2025 |
-3 -5 |
Begin Closeout Phase
End Closeout Phase |
|
|
07/31/2026 |
0 | 12/31/2025 12/31/2026 |
0 -5 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.