Bridge No. 51C0008 - ALISAL RD & SANTA YNEZ RIVER |
Description: Bridge No. 51C0008 - ALISAL RD & SANTA YNEZ RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Barbara County |
City | Solvang |
Zip Code | 93463 |
Senate District |
19 |
Assembly District | 35 |
Congressional District | 24 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Solvang | Matt van der Linden | (805) 688-5575 | mattv@cityofsolvang.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$47 | $74 | $121 | ||||
Non-bond Funding | |||||||
State/Federal* |
$360 | $744 | $1,104 | ||||
Local** |
$0 | $22 | $22 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $407 | $840 | $1,247 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $191 | $191 | $164 | $164 | $26 | |
Right of Way |
$0 | $10 | $10 | $2 | $2 | $8 | |
Construction |
$407 | $639 | $1,047 | $934 | $934 | $112 | |
Total* | $407 | $840 | $1,247 | $1,100 | $1,100 | $147 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
03/30/1997 |
|
03/30/1997 |
100 | 03/30/1997 03/31/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/30/2008 01/31/2009 |
10/15/2009 10/15/2009 |
09/30/2008 06/30/2010 |
100 | 01/28/2013 01/29/2016 |
-53 -68 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | 04/02/2015 06/30/2015 |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2011 12/31/2011 |
02/01/2012 02/01/2012 |
05/20/2014 02/20/2015 |
100 | 02/15/2016 01/20/2017 |
-21 -23 |
Begin Closeout Phase
End Closeout Phase |
01/31/2012 |
|
02/21/2015 |
100 | 02/17/2017 09/22/2017 |
-24 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.