Caltrans Logo

Bridge No. 51C0008 - ALISAL RD & SANTA YNEZ RIVER

Description: Bridge No. 51C0008 - ALISAL RD & SANTA YNEZ RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara County
City Solvang
Zip Code 93463
 
Senate District
19
Assembly District 35
Congressional District 24
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Solvang Matt van der Linden (805) 688-5575   mattv@cityofsolvang.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$47 $74 $121
Non-bond Funding
State/Federal*
$360 $744 $1,104
Local**
$0 $22 $22
Private***
$0 $0 $0
 
Total**** $407 $840 $1,247

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $191 $191 $164 $164 $26
Right of Way
$0 $10 $10 $2 $2 $8
Construction
$407 $639 $1,047 $934 $934 $112
 
Total* $407 $840 $1,247 $1,100 $1,100 $147

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

03/30/1997 
 

 
 

03/30/1997 
100  03/30/1997 

03/31/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/30/2008 

01/31/2009 
10/15/2009 

10/15/2009 
09/30/2008 

06/30/2010 
100  01/28/2013 

01/29/2016 
-53 

-68 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100  04/02/2015 

06/30/2015 


Begin Construction Phase

End Construction Phase
09/30/2011 

12/31/2011 
02/01/2012 

02/01/2012 
05/20/2014 

02/20/2015 
100  02/15/2016 

01/20/2017 
-21 

-23 
Begin Closeout Phase

End Closeout Phase
01/31/2012 

 
 

 
02/21/2015 

 
100  02/17/2017 

09/22/2017 
-24 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.