Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 51C0017 - JALAMA RD & JALAMA CREEK |
Description: Bridge No. 51C0017 - JALAMA RD & JALAMA CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Barbara County |
City | |
Zip Code | 93436 |
Senate District |
19 |
Assembly District | 33 |
Congressional District | 24 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Santa Barbara County | Chris Sneddon | (805)568-3005 | csneddo@cosbpw.net |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$128 | $116 | $244 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,134 | $4,803 | $5,937 | ||||
Local** |
$24 | $490 | $515 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,286 | $5,409 | $6,696 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$156 | $1,252 | $1,407 | $1,433 | $1,433 | $-25 | |
Right of Way |
$13 | $67 | $80 | $55 | $55 | $25 | |
Construction |
$1,117 | $4,091 | $5,208 | $4,804 | $4,814 | $394 | |
Total* | $1,286 | $5,409 | $6,696 | $6,292 | $6,302 | $394 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/30/2008 07/30/2008 |
|
01/30/2008 07/30/2008 |
100 | 01/30/2008 07/30/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/30/2008 09/30/2009 |
10/15/2009 10/15/2009 |
09/30/2008 04/30/2010 |
100 | 09/30/2008 03/23/2015 |
0 -60 |
Begin Right of Way Phase
End Right of Way Phase |
03/30/2009 09/30/2009 |
10/15/2009 10/15/2009 |
03/30/2009 04/30/2010 |
100 | 01/14/2014 05/31/2015 |
-58 -62 |
Begin Construction Phase
End Construction Phase |
11/30/2009 05/30/2010 |
10/15/2009 10/15/2009 |
08/30/2010 06/15/2011 |
100 | 03/24/2015 12/31/2018 |
-56 -92 |
Begin Closeout Phase
End Closeout Phase |
11/30/2010 |
10/15/2009 |
12/30/2011 02/28/2019 |
75 | 01/01/2019 12/23/2019 |
-85 -10 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$128,138 |
Current Approved: |
$244,175 |
Actual Expenditures: |
$227,942 |
Status as of December 31, 2023.