Caltrans Logo

Bridge No. 51C0017 - JALAMA RD & JALAMA CREEK

Description: Bridge No. 51C0017 - JALAMA RD & JALAMA CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara County
City
Zip Code 93436
 
Senate District
19
Assembly District 33
Congressional District 24
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Santa Barbara County Chris Sneddon (805)568-3005   csneddo@cosbpw.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$128 $116 $244
Non-bond Funding
State/Federal*
$1,134 $4,803 $5,937
Local**
$24 $490 $515
Private***
$0 $0 $0
 
Total**** $1,286 $5,409 $6,696

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$156 $1,252 $1,407 $1,433 $1,433 $-25
Right of Way
$13 $67 $80 $55 $55 $25
Construction
$1,117 $4,091 $5,208 $4,804 $4,814 $394
 
Total* $1,286 $5,409 $6,696 $6,292 $6,302 $394

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
01/30/2008 

07/30/2008 
 

 
01/30/2008 

07/30/2008 
100  01/30/2008 

07/30/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/30/2008 

09/30/2009 
10/15/2009 

10/15/2009 
09/30/2008 

04/30/2010 
100  09/30/2008 

03/23/2015 


-60 
Begin Right of Way Phase

End Right of Way Phase
03/30/2009 

09/30/2009 
10/15/2009 

10/15/2009 
03/30/2009 

04/30/2010 
100  01/14/2014 

05/31/2015 
-58 

-62 
Begin Construction Phase

End Construction Phase
11/30/2009 

05/30/2010 
10/15/2009 

10/15/2009 
08/30/2010 

06/15/2011 
100  03/24/2015 

12/31/2018 
-56 

-92 
Begin Closeout Phase

End Closeout Phase
11/30/2010 

 
10/15/2009 

 
12/30/2011 

02/28/2019 
75  01/01/2019 

12/23/2019 
-85 

-10 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$128,138
Current Approved:
$244,175
Actual Expenditures:
$227,942

 

Status as of December 31, 2023.