Caltrans Logo

Bridge No. 51C0018 - UP RR & AMTRAK & HOLLISTER AVENUE

Description: Bridge No. 51C0018 - UP RR & AMTRAK & HOLLISTER AVENUE - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara County
City
Zip Code 93110
 
Senate District
19
Assembly District 35
Congressional District 23
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Santa Barbara County Chris Sneddon (805) 568-3005   csneddo@cosbpw.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$130 $44 $174
Non-bond Funding
State/Federal*
$1,181 $551 $1,732
Local**
$23 $27 $50
Private***
$0 $0 $0
 
Total**** $1,334 $622 $1,956

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$200 $233 $433 $433 $433 $-0
Right of Way
$0 $38 $38 $34 $34 $3
Construction
$1,134 $351 $1,485 $1,501 $1,501 $-16
 
Total* $1,334 $622 $1,956 $1,969 $1,969 $-13

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
01/30/2008 

07/30/2008 
 

 
01/30/2008 

07/30/2008 
100  01/30/2008 

07/30/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/30/2009 

07/30/2010 
10/15/2009 

10/15/2009 
07/30/2009 

07/30/2010 
100  03/12/2008 

03/13/2012 
17 

-20 
Begin Right of Way Phase

End Right of Way Phase
 

 
10/15/2009 

10/15/2009 
10/15/2009 

07/30/2010 
100  04/13/2011 

10/18/2011 
-18 

-15 
Begin Construction Phase

End Construction Phase
10/30/2010 

04/30/2011 
10/15/2009 

10/15/2009 
10/30/2010 

04/30/2011 
100  03/14/2012 

09/10/2013 
-17 

-29 
Begin Closeout Phase

End Closeout Phase
10/30/2011 

 
10/15/2009 

 
10/30/2011 

 
50  09/10/2013 

12/23/2019 
-23 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$130,086
Current Approved:
$174,193
Actual Expenditures:
$174,193

 

Status as of December 31, 2023.