Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 51C0018 - UP RR & AMTRAK & HOLLISTER AVENUE |
Description: Bridge No. 51C0018 - UP RR & AMTRAK & HOLLISTER AVENUE - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Barbara County |
City | |
Zip Code | 93110 |
Senate District |
19 |
Assembly District | 35 |
Congressional District | 23 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Santa Barbara County | Chris Sneddon | (805) 568-3005 | csneddo@cosbpw.net |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$130 | $44 | $174 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,181 | $551 | $1,732 | ||||
Local** |
$23 | $27 | $50 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,334 | $622 | $1,956 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$200 | $233 | $433 | $433 | $433 | $-0 | |
Right of Way |
$0 | $38 | $38 | $34 | $34 | $3 | |
Construction |
$1,134 | $351 | $1,485 | $1,501 | $1,501 | $-16 | |
Total* | $1,334 | $622 | $1,956 | $1,969 | $1,969 | $-13 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/30/2008 07/30/2008 |
|
01/30/2008 07/30/2008 |
100 | 01/30/2008 07/30/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/30/2009 07/30/2010 |
10/15/2009 10/15/2009 |
07/30/2009 07/30/2010 |
100 | 03/12/2008 03/13/2012 |
17 -20 |
Begin Right of Way Phase
End Right of Way Phase |
|
10/15/2009 10/15/2009 |
10/15/2009 07/30/2010 |
100 | 04/13/2011 10/18/2011 |
-18 -15 |
Begin Construction Phase
End Construction Phase |
10/30/2010 04/30/2011 |
10/15/2009 10/15/2009 |
10/30/2010 04/30/2011 |
100 | 03/14/2012 09/10/2013 |
-17 -29 |
Begin Closeout Phase
End Closeout Phase |
10/30/2011 |
10/15/2009 |
10/30/2011 |
50 | 09/10/2013 12/23/2019 |
-23 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$130,086 |
Current Approved: |
$174,193 |
Actual Expenditures: |
$174,193 |
Status as of December 31, 2023.