Caltrans Logo

Bridge No. 51C0039 - RINCON HILL RD & RINCON CREEK

Description: Bridge No. 51C0039 - RINCON HILL RD & RINCON CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara County
City
Zip Code 93013
 
Senate District
19
Assembly District 35
Congressional District 23
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Santa Barbara County Chris Sneddon (805) 568-3005   csneddo@cosbpw.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$80 $-2 $78
Non-bond Funding
State/Federal*
$810 $-63 $748
Local**
$19 $0 $19
Private***
$0 $0 $0
 
Total**** $909 $-65 $844

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$162 $0 $162 $214 $214 $-52
Right of Way
$50 $0 $50 $16 $16 $34
Construction
$697 $-65 $632 $581 $581 $51
 
Total* $909 $-65 $844 $812 $812 $32

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
01/30/2008 

07/30/2008 
 

 
01/30/2008 

07/30/2008 
100  01/30/2008 

07/30/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/30/2009 

08/30/2010 
10/15/2009 

10/15/2009 
07/30/2009 

08/30/2010 
100  07/30/2009 

06/30/2015 


-59 
Begin Right of Way Phase

End Right of Way Phase
07/30/2010 

02/28/2011 
10/15/2009 

10/15/2009 
07/30/2010 

02/28/2011 
100  03/21/2014 

06/30/2015 
-44 

-53 
Begin Construction Phase

End Construction Phase
09/30/2011 

01/30/2012 
10/15/2009 

10/15/2009 
09/30/2011 

01/30/2012 
100  07/01/2015 

09/30/2017 
-46 

-69 
Begin Closeout Phase

End Closeout Phase
02/28/2012 

 
10/15/2009 

 
02/02/2012 

04/01/2018 
100  10/01/2017 

12/04/2019 
-69 

-20 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$85,681
Current Approved:
$77,576
Actual Expenditures:
$66,674

 

Status as of December 31, 2023.