Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 51C0039 - RINCON HILL RD & RINCON CREEK |
Description: Bridge No. 51C0039 - RINCON HILL RD & RINCON CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Barbara County |
City | |
Zip Code | 93013 |
Senate District |
19 |
Assembly District | 35 |
Congressional District | 23 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Santa Barbara County | Chris Sneddon | (805) 568-3005 | csneddo@cosbpw.net |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$80 | $-2 | $78 | ||||
Non-bond Funding | |||||||
State/Federal* |
$810 | $-63 | $748 | ||||
Local** |
$19 | $0 | $19 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $909 | $-65 | $844 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$162 | $0 | $162 | $214 | $214 | $-52 | |
Right of Way |
$50 | $0 | $50 | $16 | $16 | $34 | |
Construction |
$697 | $-65 | $632 | $581 | $581 | $51 | |
Total* | $909 | $-65 | $844 | $812 | $812 | $32 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/30/2008 07/30/2008 |
|
01/30/2008 07/30/2008 |
100 | 01/30/2008 07/30/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/30/2009 08/30/2010 |
10/15/2009 10/15/2009 |
07/30/2009 08/30/2010 |
100 | 07/30/2009 06/30/2015 |
0 -59 |
Begin Right of Way Phase
End Right of Way Phase |
07/30/2010 02/28/2011 |
10/15/2009 10/15/2009 |
07/30/2010 02/28/2011 |
100 | 03/21/2014 06/30/2015 |
-44 -53 |
Begin Construction Phase
End Construction Phase |
09/30/2011 01/30/2012 |
10/15/2009 10/15/2009 |
09/30/2011 01/30/2012 |
100 | 07/01/2015 09/30/2017 |
-46 -69 |
Begin Closeout Phase
End Closeout Phase |
02/28/2012 |
10/15/2009 |
02/02/2012 04/01/2018 |
100 | 10/01/2017 12/04/2019 |
-69 -20 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$85,681 |
Current Approved: |
$77,576 |
Actual Expenditures: |
$66,674 |
Status as of December 31, 2023.