Caltrans Logo

Bridge No. 51C0173 - SANTA ROSA ROAD & NOJOQUI CREEK

Description: Bridge No. 51C0173 - SANTA ROSA ROAD & NOJOQUI CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara County
City
Zip Code 93427
 
Senate District
19
Assembly District 35
Congressional District 24
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Santa Barbara County Chris Sneddon (805) 568-3005   csenddo@cosbpw.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$77 $90 $167
Non-bond Funding
State/Federal*
$715 $937 $1,651
Local**
$14 $29 $42
Private***
$0 $0 $0
 
Total**** $805 $1,056 $1,861

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$120 $250 $370 $342 $342 $28
Right of Way
$17 $18 $35 $40 $40 $-5
Construction
$668 $788 $1,456 $1,454 $1,454 $2
 
Total* $805 $1,056 $1,861 $1,835 $1,835 $25

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

03/11/1997 
 

 
 

03/11/1997 
100  11/08/2005 

07/30/2006 


-114 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/30/2006 

04/30/2009 
10/15/2009 

10/15/2009 
07/30/2006 

02/15/2010 
100  07/30/2006 

06/01/2011 


-16 
Begin Right of Way Phase

End Right of Way Phase
09/30/2008 

04/30/2009 
10/15/2009 

10/15/2009 
09/30/2008 

02/15/2010 
100  03/30/2009 

02/28/2011 
-6 

-13 
Begin Construction Phase

End Construction Phase
07/30/2009 

11/30/2009 
10/15/2009 

10/15/2009 
05/30/2010 

10/30/2010 
100  06/27/2011 

09/03/2013 
-13 

-35 
Begin Closeout Phase

End Closeout Phase
05/30/2010 

05/30/2010 
10/15/2009 

 
09/04/2010 

04/30/2011 
100  04/30/2011 

12/04/2019 
-8 

-105 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$78,782
Current Approved:
$166,976
Actual Expenditures:
$166,743

 

Status as of December 31, 2023.