Bridge No. 51C0250 - CHAPALA ST & MISSION CREEK

Description: Bridge No. 51C0250 - CHAPALA ST & MISSION CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara County
City Santa Barbara
Zip Code 93101
 
Senate District
19
Assembly District 35
Congressional District 23
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Santa Barbara Brian D'Amour (805) 897-2661   bdamour@santabarbaraca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$149 $-149 $0
Non-bond Funding
State/Federal*
$1,328 $-1,328 $0
Local**
$23 $-23 $0
Private***
$0 $0 $0
 
Total**** $1,500 $-1,500 $0

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$200 $-200 $0 $200 $750 $-750
Right of Way
$100 $-100 $0 $0 $291 $-291
Construction
$1,200 $-1,200 $0 $0 $2,800 $-2,800
 
Total* $1,500 $-1,500 $0 $200 $3,841 $-3,841

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/01/2008 

10/01/2008 
 

 
04/01/2008 

10/01/2008 
100  03/30/2009 

03/30/2010 
-12 

-18 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/30/2009 

01/01/2010 
 

10/15/2009 
01/30/2009 

03/31/2011 
45  04/01/2010 

09/30/2012 
-14 

-18 
Begin Right of Way Phase

End Right of Way Phase
02/28/2010 

08/01/2010 
 

10/15/2009 
02/28/2010 

12/31/2011 
10/01/2012 

01/31/2013 
-32 

-13 
Begin Construction Phase

End Construction Phase
03/30/2011 

09/30/2012 
10/15/2009 

10/15/2009 
04/01/2012 

09/30/2013 
04/01/2013 

09/30/2013 
-12 

Begin Closeout Phase

End Closeout Phase
03/01/2013 

 
 

 
03/01/2014 

 
10/01/2013 

12/31/2013 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.