Bridge No. 51C0250 - CHAPALA ST & MISSION CREEK |
Description: Bridge No. 51C0250 - CHAPALA ST & MISSION CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Barbara County |
City | Santa Barbara |
Zip Code | 93101 |
Senate District |
19 |
Assembly District | 35 |
Congressional District | 23 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Santa Barbara | Brian D'Amour | (805) 897-2661 | bdamour@santabarbaraca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$149 | $-149 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,328 | $-1,328 | $0 | ||||
Local** |
$23 | $-23 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,500 | $-1,500 | $0 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$200 | $-200 | $0 | $200 | $750 | $-750 | |
Right of Way |
$100 | $-100 | $0 | $0 | $291 | $-291 | |
Construction |
$1,200 | $-1,200 | $0 | $0 | $2,800 | $-2,800 | |
Total* | $1,500 | $-1,500 | $0 | $200 | $3,841 | $-3,841 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
04/01/2008 10/01/2008 |
|
04/01/2008 10/01/2008 |
100 | 03/30/2009 03/30/2010 |
-12 -18 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/30/2009 01/01/2010 |
10/15/2009 |
01/30/2009 03/31/2011 |
45 | 04/01/2010 09/30/2012 |
-14 -18 |
Begin Right of Way Phase
End Right of Way Phase |
02/28/2010 08/01/2010 |
10/15/2009 |
02/28/2010 12/31/2011 |
0 | 10/01/2012 01/31/2013 |
-32 -13 |
Begin Construction Phase
End Construction Phase |
03/30/2011 09/30/2012 |
10/15/2009 10/15/2009 |
04/01/2012 09/30/2013 |
0 | 04/01/2013 09/30/2013 |
-12 0 |
Begin Closeout Phase
End Closeout Phase |
03/01/2013 |
|
03/01/2014 |
0 | 10/01/2013 12/31/2013 |
5 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.