Bridge No. 53C0036 - BEVERLY BLVD & BEVERLY BLVD OH (UPRR)

Description: Bridge No. 53C0036 - BEVERLY BLVD & BEVERLY BLVD OH (UPRR) - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Pico Rivera
Zip Code 90601
 
Senate District
30
Assembly District 58
Congressional District 38
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$122 $35 $157
Non-bond Funding
State/Federal*
$1,110 $273 $1,384
Local**
$28 $0 $28
Private***
$0 $0 $0
 
Total**** $1,260 $309 $1,569

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$201 $0 $201 $698 $698 $-497
Right of Way
$0 $0 $0 $8 $8 $-8
Construction
$1,060 $309 $1,368 $1,598 $1,598 $-230
 
Total* $1,260 $309 $1,569 $2,304 $2,304 $-735

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/01/1993 

04/10/1995 
 

 
09/01/1993 

04/30/1994 
100  09/01/1993 

04/30/1994 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/1995 

03/04/2008 
 

 
05/01/1995 

02/04/2010 
100  05/10/1995 

02/04/2010 


Begin Right of Way Phase

End Right of Way Phase
06/12/2008 

06/25/2008 
 

 
12/17/2009 

10/28/2010 
100  12/17/2009 

10/28/2010 


Begin Construction Phase

End Construction Phase
09/30/2008 

10/30/2010 
 

 
05/20/2011 

01/07/2013 
100  05/20/2011 

01/07/2013 


Begin Closeout Phase

End Closeout Phase
02/28/2011 

 
 

 
01/08/2013 

11/30/2013 
100  01/08/2013 

02/13/2014 


-2 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$121,536
Current Approved:
$156,935
Actual Expenditures:
$156,935

 

Status as of December 31, 2023.