Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0045 - BEVERLY-FIRST ST & BEVERLY/GLENDALE SEP |
Description: Bridge No. 53C0045 - BEVERLY-FIRST ST & BEVERLY/GLENDALE SEP - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Los Angeles |
Zip Code | 90026 |
Senate District |
22 |
Assembly District | 45 |
Congressional District | 34 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles | Kevin Minne | 213-923-5897 | kevin.minne@lacity.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$849 | $0 | $849 | ||||
Non-bond Funding | |||||||
State/Federal* |
$9,151 | $4,939 | $14,090 | ||||
Local** |
$157 | $1,007 | $1,164 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $10,157 | $5,945 | $16,102 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$157 | $1,783 | $1,940 | $1,940 | $1,940 | $0 | |
Right of Way |
$0 | $710 | $710 | $441 | $472 | $238 | |
Construction |
$10,000 | $3,452 | $13,452 | $13,300 | $13,300 | $152 | |
Total* | $10,157 | $5,945 | $16,102 | $15,681 | $15,712 | $390 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
05/01/2001 04/03/2003 |
|
05/01/2001 04/03/2003 |
100 | 05/01/2001 04/03/2003 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/01/2003 11/09/2009 |
10/15/2009 10/15/2009 |
05/01/2003 09/06/2010 |
100 | 05/01/2003 03/31/2017 |
0 -80 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | 04/02/2014 06/19/2015 |
0 0 |
Begin Construction Phase
End Construction Phase |
04/01/2010 07/02/2012 |
10/15/2009 10/15/2009 |
02/01/2011 05/03/2013 |
100 | 09/15/2016 09/30/2020 |
-68 -90 |
Begin Closeout Phase
End Closeout Phase |
12/03/2012 |
10/15/2009 |
10/04/2013 |
50 | 10/01/2020 07/31/2024 |
-85 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$848,780 |
Current Approved: |
$848,780 |
Actual Expenditures: |
$831,347 |
Status as of December 31, 2023.