Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0070 - EAST FORK ROAD & N FK SAN GABRIEL RIV |
Description: BRIDGE NO. 53C0070 - EAST FORK ROAD & N FK SAN GABRIEL RIV - BRIDGE SEISMIC RETROFIT
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | |
Zip Code | 93563 |
Senate District |
29 |
Assembly District | 59 |
Congressional District | 26 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Mario Rodriguez | (626) 458-3950 | mrodrigu@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$177 | $152 | $329 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,586 | $1,776 | $3,361 | ||||
Local** |
$9 | $704 | $713 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,772 | $2,632 | $4,403 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$231 | $258 | $488 | $480 | $480 | $8 | |
Right of Way |
$0 | $4 | $4 | $4 | $4 | $0 | |
Construction |
$1,541 | $2,370 | $3,911 | $3,911 | $3,911 | $0 | |
Total* | $1,772 | $2,632 | $4,403 | $4,395 | $4,395 | $8 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
04/21/1995 07/09/2001 |
|
04/21/1995 07/09/2001 |
100 | 04/21/1995 07/09/2001 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/09/2001 02/12/2008 |
|
08/09/2001 10/29/2009 |
100 | 08/09/2001 10/29/2009 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/18/2007 06/12/2008 |
|
03/20/2008 04/16/2009 |
100 | 03/20/2008 04/16/2009 |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2008 10/30/2010 |
05/05/2014 05/05/2014 |
12/17/2013 12/31/2016 |
100 | 09/15/2009 10/04/2016 |
52 3 |
Begin Closeout Phase
End Closeout Phase |
02/28/2011 |
05/05/2014 |
01/01/2017 |
100 | 10/05/2016 08/28/2017 |
3 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$176,768 |
Current Approved: |
$329,229 |
Actual Expenditures: |
$329,229 |
Status as of December 31, 2023.