Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0082 - WASHINGTON BLVD & SAN GABRIEL RIVER |
Description: Bridge No. 53C0082 - WASHINGTON BLVD & SAN GABRIEL RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Pico Rivera |
Zip Code | 90606 |
Senate District |
30 |
Assembly District | 56, 58 |
Congressional District | 38, 39 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626)458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$17 | $-4 | $13 | ||||
Non-bond Funding | |||||||
State/Federal* |
$310 | $-35 | $275 | ||||
Local** |
$23 | $0 | $23 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $350 | $-39 | $311 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$199 | $0 | $199 | $169 | $169 | $30 | |
Right of Way |
$0 | $0 | $0 | $3 | $3 | $-3 | |
Construction |
$151 | $-39 | $112 | $148 | $148 | $-37 | |
Total* | $350 | $-39 | $311 | $320 | $320 | $-10 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
02/07/1995 06/01/1996 |
|
02/07/1995 06/01/1996 |
100 | 02/07/1995 06/30/1996 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/1996 01/10/2008 |
|
07/01/1996 01/10/2008 |
100 | 07/01/1996 05/14/2008 |
0 -4 |
Begin Right of Way Phase
End Right of Way Phase |
01/18/2007 07/02/2008 |
|
01/18/2007 07/02/2008 |
100 | 03/10/2008 06/24/2008 |
-14 0 |
Begin Construction Phase
End Construction Phase |
10/21/2008 04/30/2010 |
|
10/21/2008 04/30/2010 |
100 | 09/22/2008 02/01/2010 |
1 3 |
Begin Closeout Phase
End Closeout Phase |
08/30/2010 |
|
08/30/2010 |
100 | 02/02/2010 06/09/2011 |
7 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$17,308 |
Current Approved: |
$12,815 |
Actual Expenditures: |
$12,815 |
Status as of December 31, 2023.