Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0084 - SLAUSON AVE & SAN GABRIAL |
Description: Bridge No. 53C0084 - SLAUSON AVE & SAN GABRIAL - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Los Angeles County |
City | Pico Rivera, Santa Fe Springs |
Zip Code | 90660 |
Senate District |
30 |
Assembly District | 56, 64 |
Congressional District | 38 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Masashi Tsujii | (626) 458-3950 | mtsujii@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$129 | $78 | $207 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,080 | $518 | $1,599 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,209 | $597 | $1,806 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $0 | $0 | $1,987 | $2,320 | $-2,320 | |
Right of Way |
$0 | $0 | $0 | $13 | $15 | $-15 | |
Construction |
$1,209 | $597 | $1,806 | $0 | $1,806 | $0 | |
Total* | $1,209 | $597 | $1,806 | $2,000 | $4,141 | $-2,335 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
02/07/1995 06/01/1996 |
|
02/07/1995 06/01/1996 |
100 | 02/07/1995 06/30/1996 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/1996 10/31/2007 |
|
07/01/1996 07/10/2018 |
95 | 07/01/1996 10/16/2025 |
0 -88 |
Begin Right of Way Phase
End Right of Way Phase |
06/14/2007 04/26/2008 |
|
07/28/2008 01/05/2022 |
96 | 07/28/2008 06/25/2025 |
0 -42 |
Begin Construction Phase
End Construction Phase |
09/30/2008 10/30/2010 |
|
04/07/2022 10/13/2023 |
0 | 10/16/2025 09/30/2027 |
-43 -48 |
Begin Closeout Phase
End Closeout Phase |
|
|
03/29/2024 |
0 | 10/01/2027 03/31/2028 |
0 -49 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.