Bridge No. 53C0084 - SLAUSON AVE & SAN GABRIAL

Description: Bridge No. 53C0084 - SLAUSON AVE & SAN GABRIAL - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles County
City Pico Rivera, Santa Fe Springs
Zip Code 90660
 
Senate District
30
Assembly District 56, 64
Congressional District 38
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Masashi Tsujii (626) 458-3950   mtsujii@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$129 $78 $207
Non-bond Funding
State/Federal*
$1,080 $518 $1,599
Local**
$0 $0 $0
Private***
$0 $0 $0
 
Total**** $1,209 $597 $1,806

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $0 $0 $1,987 $2,320 $-2,320
Right of Way
$0 $0 $0 $13 $15 $-15
Construction
$1,209 $597 $1,806 $0 $1,806 $0
 
Total* $1,209 $597 $1,806 $2,000 $4,141 $-2,335

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
02/07/1995 

06/01/1996 
 

 
02/07/1995 

06/01/1996 
100  02/07/1995 

06/30/1996 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/1996 

10/31/2007 
 

 
07/01/1996 

07/10/2018 
95  07/01/1996 

10/16/2025 


-88 
Begin Right of Way Phase

End Right of Way Phase
06/14/2007 

04/26/2008 
 

 
07/28/2008 

01/05/2022 
96  07/28/2008 

06/25/2025 


-42 
Begin Construction Phase

End Construction Phase
09/30/2008 

10/30/2010 
 

 
04/07/2022 

10/13/2023 
10/16/2025 

09/30/2027 
-43 

-48 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

03/29/2024 
10/01/2027 

03/31/2028 


-49 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.