Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0085 - FLORENCE AVE & RIO HONDO |
Description: Bridge No. 53C0085 - FLORENCE AVE & RIO HONDO - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Bell Gardens, Downey |
Zip Code | 90201, 90241 |
Senate District |
27, 30 |
Assembly District | 50, 58 |
Congressional District | 34 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$50 | $-17 | $33 | ||||
Non-bond Funding | |||||||
State/Federal* |
$556 | $-129 | $427 | ||||
Local** |
$24 | $0 | $24 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $630 | $-146 | $484 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$194 | $0 | $194 | $419 | $419 | $-226 | |
Right of Way |
$0 | $0 | $0 | $4 | $4 | $-4 | |
Construction |
$436 | $-146 | $291 | $363 | $363 | $-73 | |
Total* | $630 | $-146 | $484 | $786 | $786 | $-302 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
09/01/1993 03/26/1995 |
|
09/01/1993 03/26/1995 |
100 | 09/01/1993 04/25/1995 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/26/1995 04/03/2007 |
|
04/26/1995 04/03/2007 |
100 | 04/26/1995 07/01/2008 |
0 -15 |
Begin Right of Way Phase
End Right of Way Phase |
01/18/2007 02/12/2008 |
|
01/18/2007 02/12/2008 |
100 | 02/20/2008 07/11/2008 |
-13 -5 |
Begin Construction Phase
End Construction Phase |
05/29/2008 11/30/2009 |
10/15/2009 10/15/2009 |
09/22/2008 10/31/2010 |
100 | 09/22/2008 03/17/2010 |
0 8 |
Begin Closeout Phase
End Closeout Phase |
03/30/2010 |
10/15/2009 |
02/28/2011 |
50 | 10/27/2010 |
4 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$50,057 |
Current Approved: |
$33,325 |
Actual Expenditures: |
$33,325 |
Status as of December 31, 2023.