Bridge No. 53C0085 - FLORENCE AVE & RIO HONDO

Description: Bridge No. 53C0085 - FLORENCE AVE & RIO HONDO - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Bell Gardens, Downey
Zip Code 90201, 90241
 
Senate District
27, 30
Assembly District 50, 58
Congressional District 34
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$50 $-17 $33
Non-bond Funding
State/Federal*
$556 $-129 $427
Local**
$24 $0 $24
Private***
$0 $0 $0
 
Total**** $630 $-146 $484

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$194 $0 $194 $419 $419 $-226
Right of Way
$0 $0 $0 $4 $4 $-4
Construction
$436 $-146 $291 $363 $363 $-73
 
Total* $630 $-146 $484 $786 $786 $-302

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/01/1993 

03/26/1995 
 

 
09/01/1993 

03/26/1995 
100  09/01/1993 

04/25/1995 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/26/1995 

04/03/2007 
 

 
04/26/1995 

04/03/2007 
100  04/26/1995 

07/01/2008 


-15 
Begin Right of Way Phase

End Right of Way Phase
01/18/2007 

02/12/2008 
 

 
01/18/2007 

02/12/2008 
100  02/20/2008 

07/11/2008 
-13 

-5 
Begin Construction Phase

End Construction Phase
05/29/2008 

11/30/2009 
10/15/2009 

10/15/2009 
09/22/2008 

10/31/2010 
100  09/22/2008 

03/17/2010 


Begin Closeout Phase

End Closeout Phase
03/30/2010 

 
10/15/2009 

 
02/28/2011 

 
50  10/27/2010 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$50,057
Current Approved:
$33,325
Actual Expenditures:
$33,325

 

Status as of December 31, 2023.