Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0096 - FLETCHER DR & LOS ANGELES RIVER |
Description: Bridge No. 53C0096 - FLETCHER DR & LOS ANGELES RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Los Angeles |
Zip Code | 90039 |
Senate District |
21 |
Assembly District | 45 |
Congressional District | 31 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles | Shirley Lau | (213) 485-5228 | Shirley.Lau@lacity.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$849 | $274 | $1,123 | ||||
Non-bond Funding | |||||||
State/Federal* |
$7,302 | $2,252 | $9,554 | ||||
Local** |
$188 | $18 | $205 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $8,338 | $2,544 | $10,882 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$938 | $153 | $1,091 | $1,327 | $1,091 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$7,400 | $2,390 | $9,790 | $9,944 | $10,200 | $-410 | |
Total* | $8,338 | $2,544 | $10,882 | $11,271 | $11,292 | $-410 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
10/04/2001 07/21/2003 |
|
10/04/2001 07/21/2003 |
100 | 10/04/2001 07/21/2003 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/05/2004 07/31/2009 |
|
10/05/2004 05/30/2008 |
100 | 10/05/2004 05/30/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/04/2010 01/03/2012 |
10/15/2009 10/15/2009 |
06/30/2009 09/30/2012 |
100 | 06/30/2009 08/30/2013 |
0 -11 |
Begin Closeout Phase
End Closeout Phase |
05/02/2012 |
10/15/2009 |
03/05/2013 |
100 | 09/03/2013 06/30/2019 |
-6 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$848,780 |
Current Approved: |
$1,122,955 |
Actual Expenditures: |
$926,946 |
Status as of December 31, 2023.