Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0106 - IMPERIAL HIGHWAY & SAN GABRIEL RIV & FRT RD |
Description: BRIDGE NO. 53C0106 - IMPERIAL HIGHWAY & SAN GABRIEL RIV & FRT RD - BRIDGE SEISMIC RETROFIT
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Downey, Norwalk |
Zip Code | 90242, 90650 |
Senate District |
27, 30 |
Assembly District | 50, 56 |
Congressional District | 34, 38 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$143 | $-25 | $118 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,305 | $-193 | $1,112 | ||||
Local** |
$16 | $0 | $16 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,463 | $-218 | $1,245 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$221 | $0 | $221 | $412 | $412 | $-192 | |
Right of Way |
$0 | $0 | $0 | $2 | $2 | $-2 | |
Construction |
$1,243 | $-218 | $1,025 | $1,033 | $1,033 | $-9 | |
Total* | $1,463 | $-218 | $1,245 | $1,447 | $1,447 | $-202 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
09/01/1993 04/24/2001 |
|
09/01/1993 04/24/2001 |
100 | 09/01/1993 04/24/2001 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/24/2001 04/03/2007 |
|
05/24/2001 04/03/2007 |
100 | 05/24/2001 01/29/2007 |
0 2 |
Begin Right of Way Phase
End Right of Way Phase |
01/18/2007 07/30/2007 |
|
01/18/2007 07/30/2007 |
100 | 07/02/2007 07/18/2007 |
-5 0 |
Begin Construction Phase
End Construction Phase |
09/18/2007 09/30/2009 |
|
09/18/2007 09/30/2009 |
100 | 09/18/2007 06/02/2009 |
0 4 |
Begin Closeout Phase
End Closeout Phase |
01/30/2010 |
|
01/30/2010 |
100 | 06/03/2009 12/21/2011 |
8 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$142,516 |
Current Approved: |
$117,518 |
Actual Expenditures: |
$117,037 |
Status as of December 31, 2023.