Caltrans Logo

Bridge No. 53C0178 - VALLEY BLVD & SP/UP RR

Description: Bridge No. 53C0178 - VALLEY BLVD & SP/UP RR - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Industry
Zip Code 91744, 91748
 
Senate District
24
Assembly District 57, 58
Congressional District 38
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$286 $-49 $237
Non-bond Funding
State/Federal*
$2,423 $-381 $2,041
Local**
$38 $0 $38
Private***
$0 $0 $0
 
Total**** $2,747 $-431 $2,316

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$252 $0 $252 $580 $580 $-329
Right of Way
$0 $0 $0 $3 $3 $-3
Construction
$2,495 $-431 $2,064 $2,364 $2,364 $-300
 
Total* $2,747 $-431 $2,316 $2,948 $2,948 $-632

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/01/1993 

11/05/1995 
 

 
09/01/1993 

11/05/1995 
100  09/01/1993 

12/04/1994 


11 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/05/1995 

12/17/2007 
 

 
12/05/1995 

09/08/2008 
100  12/05/1995 

09/08/2008 


Begin Right of Way Phase

End Right of Way Phase
05/15/2008 

06/02/2008 
 

 
09/09/2008 

05/20/2009 
100  09/09/2008 

05/20/2009 


Begin Construction Phase

End Construction Phase
10/01/2008 

04/30/2011 
10/15/2009 

10/15/2009 
09/15/2009 

05/31/2011 
100  09/15/2009 

12/14/2011 


-7 
Begin Closeout Phase

End Closeout Phase
08/30/2011 

 
10/15/2009 

 
07/31/2012 

 
100  12/15/2011 

09/20/2012 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$286,183
Current Approved:
$236,783
Actual Expenditures:
$236,783

 

Status as of December 31, 2023.