Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0178 - VALLEY BLVD & SP/UP RR |
Description: Bridge No. 53C0178 - VALLEY BLVD & SP/UP RR - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Industry |
Zip Code | 91744, 91748 |
Senate District |
24 |
Assembly District | 57, 58 |
Congressional District | 38 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$286 | $-49 | $237 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,423 | $-381 | $2,041 | ||||
Local** |
$38 | $0 | $38 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $2,747 | $-431 | $2,316 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$252 | $0 | $252 | $580 | $580 | $-329 | |
Right of Way |
$0 | $0 | $0 | $3 | $3 | $-3 | |
Construction |
$2,495 | $-431 | $2,064 | $2,364 | $2,364 | $-300 | |
Total* | $2,747 | $-431 | $2,316 | $2,948 | $2,948 | $-632 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
09/01/1993 11/05/1995 |
|
09/01/1993 11/05/1995 |
100 | 09/01/1993 12/04/1994 |
0 11 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/05/1995 12/17/2007 |
|
12/05/1995 09/08/2008 |
100 | 12/05/1995 09/08/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
05/15/2008 06/02/2008 |
|
09/09/2008 05/20/2009 |
100 | 09/09/2008 05/20/2009 |
0 0 |
Begin Construction Phase
End Construction Phase |
10/01/2008 04/30/2011 |
10/15/2009 10/15/2009 |
09/15/2009 05/31/2011 |
100 | 09/15/2009 12/14/2011 |
0 -7 |
Begin Closeout Phase
End Closeout Phase |
08/30/2011 |
10/15/2009 |
07/31/2012 |
100 | 12/15/2011 09/20/2012 |
8 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$286,183 |
Current Approved: |
$236,783 |
Actual Expenditures: |
$236,783 |
Status as of December 31, 2023.