Bridge No. 53C0261 - AVALON BLVD & DOMINGUEZ CHANNEL |
Description: Bridge No. 53C0261 - AVALON BLVD & DOMINGUEZ CHANNEL - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Carson |
Zip Code | 90745, 90746 |
Senate District |
28 |
Assembly District | 55 |
Congressional District | 37 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$24 | $7 | $31 | ||||
Non-bond Funding | |||||||
State/Federal* |
$310 | $55 | $366 | ||||
Local** |
$1 | $0 | $1 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $335 | $62 | $398 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$130 | $0 | $130 | $478 | $478 | $-348 | |
Right of Way |
$0 | $0 | $0 | $5 | $5 | $-5 | |
Construction |
$206 | $62 | $268 | $283 | $283 | $-15 | |
Total* | $335 | $62 | $398 | $766 | $766 | $-368 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
02/07/1995 10/02/1995 |
|
02/07/1995 10/02/1995 |
100 | 02/07/1995 11/01/1995 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/02/1995 03/11/2008 |
|
11/02/1995 03/11/2008 |
100 | 11/02/1995 05/14/2008 |
0 -2 |
Begin Right of Way Phase
End Right of Way Phase |
01/18/2007 07/31/2008 |
|
01/18/2007 07/31/2008 |
100 | 06/02/2008 07/07/2008 |
-17 1 |
Begin Construction Phase
End Construction Phase |
11/26/2008 05/30/2010 |
03/01/2010 |
09/22/2008 05/30/2010 |
100 | 09/22/2008 02/03/2010 |
0 4 |
Begin Closeout Phase
End Closeout Phase |
09/30/2010 |
|
09/30/2010 |
100 | 02/04/2010 07/18/2011 |
8 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$23,581 |
Current Approved: |
$30,718 |
Actual Expenditures: |
$30,718 |
Status as of December 31, 2023.