Caltrans Logo

Bridge No. 53C0261 - AVALON BLVD & DOMINGUEZ CHANNEL

Description: Bridge No. 53C0261 - AVALON BLVD & DOMINGUEZ CHANNEL - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Carson
Zip Code 90745, 90746
 
Senate District
28
Assembly District 55
Congressional District 37
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$24 $7 $31
Non-bond Funding
State/Federal*
$310 $55 $366
Local**
$1 $0 $1
Private***
$0 $0 $0
 
Total**** $335 $62 $398

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$130 $0 $130 $478 $478 $-348
Right of Way
$0 $0 $0 $5 $5 $-5
Construction
$206 $62 $268 $283 $283 $-15
 
Total* $335 $62 $398 $766 $766 $-368

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
02/07/1995 

10/02/1995 
 

 
02/07/1995 

10/02/1995 
100  02/07/1995 

11/01/1995 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/02/1995 

03/11/2008 
 

 
11/02/1995 

03/11/2008 
100  11/02/1995 

05/14/2008 


-2 
Begin Right of Way Phase

End Right of Way Phase
01/18/2007 

07/31/2008 
 

 
01/18/2007 

07/31/2008 
100  06/02/2008 

07/07/2008 
-17 

Begin Construction Phase

End Construction Phase
11/26/2008 

05/30/2010 
03/01/2010 

 
09/22/2008 

05/30/2010 
100  09/22/2008 

02/03/2010 


Begin Closeout Phase

End Closeout Phase
09/30/2010 

 
 

 
09/30/2010 

 
100  02/04/2010 

07/18/2011 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$23,581
Current Approved:
$30,718
Actual Expenditures:
$30,718

 

Status as of December 31, 2023.