Bridge No. 53C0266 - WILLOW ST & COYOTE CREEK |
Description: Bridge No. 53C0266 - WILLOW ST & COYOTE CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Long Beach, Los Alamitos |
Zip Code | 90720, 90815 |
Senate District |
27, 35 |
Assembly District | 54, 67 |
Congressional District | 40, 46 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$34 | $0 | $34 | ||||
Non-bond Funding | |||||||
State/Federal* |
$433 | $3 | $436 | ||||
Local** |
$60 | $0 | $60 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $526 | $3 | $530 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$201 | $0 | $201 | $290 | $290 | $-89 | |
Right of Way |
$0 | $0 | $0 | $1 | $1 | $-1 | |
Construction |
$326 | $3 | $329 | $343 | $343 | $-14 | |
Total* | $526 | $3 | $530 | $633 | $633 | $-103 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
09/01/1993 04/10/1995 |
|
09/01/1993 04/10/1995 |
100 | 09/01/1993 04/30/1995 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/01/1995 12/11/2007 |
10/15/2009 |
05/01/1995 01/25/2007 |
100 | 05/01/1995 01/25/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/18/2007 06/18/2007 |
10/15/2009 |
01/18/2007 07/06/2007 |
100 | 06/05/2007 07/06/2007 |
-5 0 |
Begin Construction Phase
End Construction Phase |
09/18/2007 03/30/2009 |
10/15/2009 10/15/2009 |
09/18/2007 04/14/2009 |
100 | 09/18/2007 04/14/2009 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
07/30/2009 |
|
07/30/2009 |
100 | 09/01/2010 |
-13 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$33,703 |
Current Approved: |
$34,103 |
Actual Expenditures: |
$34,103 |
Status as of December 31, 2023.