Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0375 - FOOTHILL BLVD & SAN GABRIEL RIVER |
Description: Bridge No. 53C0375 - FOOTHILL BLVD & SAN GABRIEL RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Irwindale |
Zip Code | 91010, 91706 |
Senate District |
24 |
Assembly District | 44, 57 |
Congressional District | 32 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$282 | $5 | $288 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,400 | $42 | $2,442 | ||||
Local** |
$9 | $0 | $9 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $2,691 | $48 | $2,739 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$231 | $0 | $231 | $704 | $704 | $-473 | |
Right of Way |
$0 | $0 | $0 | $6 | $6 | $-6 | |
Construction |
$2,461 | $48 | $2,509 | $2,640 | $2,640 | $-132 | |
Total* | $2,691 | $48 | $2,739 | $3,350 | $3,350 | $-611 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
04/21/1995 07/09/2001 |
|
04/21/1995 07/09/2001 |
100 | 04/21/1995 07/09/2001 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/09/2001 12/11/2007 |
|
08/09/2001 09/03/2009 |
100 | 08/09/2001 09/03/2009 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/18/2007 05/15/2008 |
|
09/01/2009 10/05/2009 |
100 | 09/01/2009 10/05/2009 |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2008 03/30/2011 |
|
04/27/2010 12/10/2012 |
100 | 04/27/2010 12/10/2012 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
07/30/2011 |
|
12/11/2012 11/30/2013 |
100 | 12/11/2012 11/27/2013 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$282,257 |
Current Approved: |
$287,750 |
Actual Expenditures: |
$287,750 |
Status as of December 31, 2023.