Caltrans Logo

Bridge No. 53C0375 - FOOTHILL BLVD & SAN GABRIEL RIVER

Description: Bridge No. 53C0375 - FOOTHILL BLVD & SAN GABRIEL RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Irwindale
Zip Code 91010, 91706
 
Senate District
24
Assembly District 44, 57
Congressional District 32
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$282 $5 $288
Non-bond Funding
State/Federal*
$2,400 $42 $2,442
Local**
$9 $0 $9
Private***
$0 $0 $0
 
Total**** $2,691 $48 $2,739

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$231 $0 $231 $704 $704 $-473
Right of Way
$0 $0 $0 $6 $6 $-6
Construction
$2,461 $48 $2,509 $2,640 $2,640 $-132
 
Total* $2,691 $48 $2,739 $3,350 $3,350 $-611

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/21/1995 

07/09/2001 
 

 
04/21/1995 

07/09/2001 
100  04/21/1995 

07/09/2001 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/09/2001 

12/11/2007 
 

 
08/09/2001 

09/03/2009 
100  08/09/2001 

09/03/2009 


Begin Right of Way Phase

End Right of Way Phase
01/18/2007 

05/15/2008 
 

 
09/01/2009 

10/05/2009 
100  09/01/2009 

10/05/2009 


Begin Construction Phase

End Construction Phase
09/30/2008 

03/30/2011 
 

 
04/27/2010 

12/10/2012 
100  04/27/2010 

12/10/2012 


Begin Closeout Phase

End Closeout Phase
07/30/2011 

 
 

 
12/11/2012 

11/30/2013 
100  12/11/2012 

11/27/2013 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$282,257
Current Approved:
$287,750
Actual Expenditures:
$287,750

 

Status as of December 31, 2023.