Bridge No. 53C0377 - FOOTHILL BLVD & LACMTA & BNSF RY

Description: Bridge No. 53C0377 - FOOTHILL BLVD & LACMTA & BNSF RY - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Azusa
Zip Code 91702
 
Senate District
24
Assembly District 57
Congressional District 32
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$72 $-11 $61
Non-bond Funding
State/Federal*
$800 $-167 $633
Local**
$30 $0 $30
Private***
$0 $0 $0
 
Total**** $902 $-178 $724

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$275 $-81 $194 $421 $421 $-227
Right of Way
$0 $0 $0 $2 $2 $-2
Construction
$627 $-97 $530 $681 $681 $-151
 
Total* $902 $-178 $724 $1,104 $1,104 $-380

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/21/1995 

05/13/2001 
 

 
04/21/1995 

05/13/2001 
100  04/21/1995 

05/13/2001 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/14/2001 

10/29/2008 
 

 
05/14/2001 

10/29/2008 
100  05/14/2001 

10/29/2008 


Begin Right of Way Phase

End Right of Way Phase
01/17/2008 

02/04/2009 
 

 
01/17/2008 

02/04/2009 
100  07/07/2008 

02/04/2009 
-6 

Begin Construction Phase

End Construction Phase
05/05/2008 

01/31/2011 
10/15/2009 

10/15/2009 
09/15/2009 

02/28/2013 
100  09/15/2009 

07/14/2011 


20 
Begin Closeout Phase

End Closeout Phase
03/30/2010 

 
 

 
03/01/2013 

 
100  07/15/2011 

06/19/2012 
20 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$71,923
Current Approved:
$60,835
Actual Expenditures:
$60,835

 

Status as of December 31, 2023.