Caltrans Logo

Bridge No. 53C0445 - SLAUSON AVE & LOS ANGELES RIVER

Description: Bridge No. 53C0445 - SLAUSON AVE & LOS ANGELES RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Bell
Zip Code 90040, 90270
 
Senate District
22, 30
Assembly District 46, 50
Congressional District 34
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$267 $-58 $209
Non-bond Funding
State/Federal*
$2,262 $-449 $1,813
Local**
$27 $0 $27
Private***
$0 $0 $0
 
Total**** $2,555 $-507 $2,048

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$225 $0 $225 $503 $503 $-278
Right of Way
$0 $0 $0 $9 $9 $-9
Construction
$2,330 $-507 $1,823 $1,844 $1,844 $-21
 
Total* $2,555 $-507 $2,048 $2,356 $2,356 $-307

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/21/1995 

08/03/1997 
 

 
04/21/1995 

08/03/1997 
100  04/21/1995 

08/03/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/03/1997 

03/28/2007 
 

 
09/03/1997 

02/05/2007 
100  09/03/1997 

02/05/2007 


Begin Right of Way Phase

End Right of Way Phase
01/18/2007 

11/29/2007 
 

 
01/18/2007 

12/14/2007 
100  11/26/2007 

12/14/2007 
-10 

Begin Construction Phase

End Construction Phase
03/11/2008 

09/30/2010 
10/15/2009 

10/15/2009 
07/03/2008 

09/30/2010 
100  07/03/2008 

06/09/2010 


Begin Closeout Phase

End Closeout Phase
01/30/2011 

 
10/15/2009 

 
01/30/2011 

 
100  06/10/2010 

11/29/2011 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$267,255
Current Approved:
$209,093
Actual Expenditures:
$209,093

 

Status as of December 31, 2023.