Bridge No. 53C0458 - UP RR & SANTA FE AVE

Description: Bridge No. 53C0458 - UP RR & SANTA FE AVE - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Carson
Zip Code 90810
 
Senate District
25
Assembly District 55
Congressional District 37
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$28 $5 $32
Non-bond Funding
State/Federal*
$437 $38 $476
Local**
$56 $0 $56
Private***
$0 $0 $0
 
Total**** $520 $43 $564

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$246 $0 $246 $278 $278 $-32
Right of Way
$0 $0 $0 $2 $2 $-2
Construction
$275 $43 $318 $389 $389 $-71
 
Total* $520 $43 $564 $668 $668 $-105

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/21/1995 

04/06/2002 
 

05/03/2010 
04/21/1995 

05/05/2002 
100  04/21/1995 

05/05/2002 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/06/2002 

09/06/2007 
 

 
05/06/2002 

09/06/2007 
100  05/06/2002 

09/06/2007 


Begin Right of Way Phase

End Right of Way Phase
12/19/2007 

01/03/2008 
 

 
12/19/2007 

04/24/2008 
100  09/20/2007 

04/24/2008 


Begin Construction Phase

End Construction Phase
04/22/2008 

10/30/2009 
 

10/15/2009 
07/11/2008 

09/29/2009 
100  07/11/2008 

09/29/2009 


Begin Closeout Phase

End Closeout Phase
02/28/2010 

 
10/15/2009 

 
02/28/2010 

 
100  09/30/2009 

07/13/2011 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$27,526
Current Approved:
$32,388
Actual Expenditures:
$32,388

 

Status as of December 31, 2023.