Bridge No. 53C0459 - WILMINGTON AV 223 & DOMINGUEZ CHANNEL |
Description: Bridge No. 53C0459 - WILMINGTON AV 223 & DOMINGUEZ CHANNEL - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Carson |
Zip Code | 90745, 90810 |
Senate District |
35 |
Assembly District | 64 |
Congressional District | 44 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Carson | Raymond Velasco | (310) 830-7600 | rvelasco@carson.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$150 | $81 | $231 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,159 | $624 | $1,783 | ||||
Local** |
$128 | $0 | $128 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,437 | $705 | $2,142 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,437 | $705 | $2,142 | $1,493 | $1,493 | $649 | |
Total* | $1,437 | $705 | $2,142 | $1,493 | $1,493 | $649 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
04/21/1995 05/29/2001 |
|
04/21/1995 05/29/2001 |
100 | 04/21/1995 05/29/2001 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/30/2001 02/28/2008 |
|
05/30/2001 02/28/2008 |
100 | 05/30/2001 01/17/2008 |
0 1 |
Begin Right of Way Phase
End Right of Way Phase |
12/14/2006 06/04/2008 |
|
08/28/2008 03/24/2009 |
100 | 08/28/2008 11/26/2012 |
0 -45 |
Begin Construction Phase
End Construction Phase |
09/30/2008 10/30/2010 |
06/12/2013 |
05/31/2013 01/31/2017 |
100 | 05/03/2013 01/31/2017 |
1 0 |
Begin Closeout Phase
End Closeout Phase |
02/28/2011 |
06/12/2013 |
02/01/2017 |
50 | 02/01/2017 03/01/2020 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$150,166 |
Current Approved: |
$231,045 |
Actual Expenditures: |
$171,243 |
Status as of December 31, 2023.