Bridge No. 53C0531 - AT & SF RR & ALOSTA AVE UNDER AT & SF

Description: Bridge No. 53C0531 - AT & SF RR & ALOSTA AVE UNDER AT & SF - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Glendora
Zip Code 91740, 91741
 
Senate District
29
Assembly District 59
Congressional District 26
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$79 $10 $89
Non-bond Funding
State/Federal*
$828 $81 $909
Local**
$29 $0 $29
Private***
$0 $0 $0
 
Total**** $936 $91 $1,027

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$249 $0 $249 $442 $442 $-193
Right of Way
$0 $0 $0 $2 $2 $-2
Construction
$687 $91 $778 $885 $885 $-107
 
Total* $936 $91 $1,027 $1,329 $1,329 $-302

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/21/1995 

09/15/1997 
 

 
04/21/1995 

09/15/1997 
100  04/21/1995 

10/14/1997 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/15/1997 

02/12/2008 
 

 
10/15/1997 

02/12/2008 
100  10/15/1997 

12/18/2008 


-10 
Begin Right of Way Phase

End Right of Way Phase
05/21/2008 

06/05/2008 
 

 
01/02/2009 

04/10/2009 
100  01/02/2009 

04/10/2009 


Begin Construction Phase

End Construction Phase
09/30/2008 

10/30/2010 
 

 
09/15/2009 

02/28/2013 
100  09/15/2009 

08/04/2011 


19 
Begin Closeout Phase

End Closeout Phase
02/28/2011 

 
 

 
03/01/2013 

 
100  08/05/2011 

06/07/2012 
19 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$78,834
Current Approved:
$89,294
Actual Expenditures:
$89,294

 

Status as of December 31, 2023.