Bridge No. 53C0575 - ARTESIA BLVD & LOS ANGELES RIVER

Description: Bridge No. 53C0575 - ARTESIA BLVD & LOS ANGELES RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Long Beach
Zip Code 90805
 
Senate District
25
Assembly District 52
Congressional District 37
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$99 $-39 $60
Non-bond Funding
State/Federal*
$987 $-298 $688
Local**
$9 $0 $9
Private***
$0 $0 $0
 
Total**** $1,095 $-337 $758

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$231 $0 $231 $667 $667 $-437
Right of Way
$0 $0 $0 $285 $285 $-285
Construction
$864 $-337 $527 $767 $767 $-240
 
Total* $1,095 $-337 $758 $1,719 $1,719 $-961

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/21/1995 

07/09/2001 
 

 
04/21/1995 

07/09/2001 
100  04/21/1995 

07/09/2001 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/09/2001 

02/11/2007 
 

 
08/09/2001 

02/11/2007 
100  08/09/2001 

02/11/2007 


Begin Right of Way Phase

End Right of Way Phase
12/07/2006 

02/26/2008 
 

 
12/07/2006 

02/26/2008 
100  12/06/2006 

07/03/2008 


-4 
Begin Construction Phase

End Construction Phase
05/28/2008 

05/30/2010 
10/15/2009 

10/15/2009 
09/22/2008 

05/30/2010 
100  09/22/2008 

03/23/2010 


Begin Closeout Phase

End Closeout Phase
09/30/2010 

 
 

 
09/30/2010 

 
100  03/24/2010 

04/12/2011 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$99,157
Current Approved:
$60,486
Actual Expenditures:
$60,486

 

Status as of December 31, 2023.