Bridge No. 53C0596 - AT&SF RR & COLORADO BLVD UP

Description: Bridge No. 53C0596 - AT&SF RR & COLORADO BLVD UP - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Arcadia
Zip Code 91006
 
Senate District
29
Assembly District 44
Congressional District 26
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$23 $0 $23
Non-bond Funding
State/Federal*
$453 $4 $457
Local**
$36 $0 $36
Private***
$0 $0 $0
 
Total**** $512 $4 $517

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$312 $0 $312 $288 $288 $24
Right of Way
$0 $0 $0 $3 $3 $-3
Construction
$200 $4 $204 $143 $143 $61
 
Total* $512 $4 $517 $435 $435 $82

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
02/07/1995 

04/24/2001 
 

 
02/07/1995 

04/24/2001 
100  02/07/1995 

05/23/2001 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/24/2001 

10/03/2007 
 

 
05/24/2001 

10/03/2007 
100  05/24/2001 

10/03/2007 


Begin Right of Way Phase

End Right of Way Phase
03/14/2008 

06/01/2008 
 

10/15/2009 
03/14/2008 

07/29/2009 
100  03/14/2008 

07/29/2009 


Begin Construction Phase

End Construction Phase
09/30/2008 

02/28/2010 
10/15/2009 

 
09/15/2009 

07/12/2011 
100  09/15/2009 

07/12/2011 


Begin Closeout Phase

End Closeout Phase
06/30/2010 

 
 

 
07/13/2011 

12/20/2012 
100  07/13/2011 

12/20/2012 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$22,929
Current Approved:
$23,149
Actual Expenditures:
$16,151

 

Status as of December 31, 2023.