Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0599 - ALAMEDA ST & COMPTON CREEK |
Description: Bridge No. 53C0599 - ALAMEDA ST & COMPTON CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Compton |
Zip Code | 90220, 90221 |
Senate District |
25 |
Assembly District | 52 |
Congressional District | 37 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$409 | $-278 | $132 | ||||
Non-bond Funding | |||||||
State/Federal* |
$3,461 | $-2,142 | $1,319 | ||||
Local** |
$44 | $0 | $44 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $3,915 | $-2,420 | $1,495 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$345 | $0 | $345 | $957 | $957 | $-611 | |
Right of Way |
$0 | $0 | $0 | $5 | $5 | $-5 | |
Construction |
$3,570 | $-2,420 | $1,150 | $1,449 | $1,449 | $-299 | |
Total* | $3,915 | $-2,420 | $1,495 | $2,411 | $2,411 | $-916 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
04/21/1995 04/24/2001 |
|
06/01/1996 04/24/2001 |
100 | 06/01/1996 02/28/2001 |
0 2 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/24/2001 10/03/2007 |
10/15/2009 |
05/24/2001 06/30/2010 |
100 | 05/24/2001 07/27/2010 |
0 -1 |
Begin Right of Way Phase
End Right of Way Phase |
01/18/2007 01/24/2008 |
10/15/2009 10/15/2009 |
07/01/2010 09/30/2010 |
100 | 05/12/2010 10/27/2010 |
2 -1 |
Begin Construction Phase
End Construction Phase |
05/12/2008 05/30/2011 |
10/15/2009 10/15/2009 |
05/31/2011 05/31/2013 |
100 | 05/20/2011 04/08/2013 |
0 2 |
Begin Closeout Phase
End Closeout Phase |
09/30/2011 |
|
11/30/2013 |
100 | 04/09/2013 11/06/2014 |
8 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$409,441 |
Current Approved: |
$131,923 |
Actual Expenditures: |
$131,923 |
Status as of December 31, 2023.