Caltrans Logo

Bridge No. 53C0599 - ALAMEDA ST & COMPTON CREEK

Description: Bridge No. 53C0599 - ALAMEDA ST & COMPTON CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Compton
Zip Code 90220, 90221
 
Senate District
25
Assembly District 52
Congressional District 37
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$409 $-278 $132
Non-bond Funding
State/Federal*
$3,461 $-2,142 $1,319
Local**
$44 $0 $44
Private***
$0 $0 $0
 
Total**** $3,915 $-2,420 $1,495

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$345 $0 $345 $957 $957 $-611
Right of Way
$0 $0 $0 $5 $5 $-5
Construction
$3,570 $-2,420 $1,150 $1,449 $1,449 $-299
 
Total* $3,915 $-2,420 $1,495 $2,411 $2,411 $-916

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/21/1995 

04/24/2001 
 

 
06/01/1996 

04/24/2001 
100  06/01/1996 

02/28/2001 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/24/2001 

10/03/2007 
 

10/15/2009 
05/24/2001 

06/30/2010 
100  05/24/2001 

07/27/2010 


-1 
Begin Right of Way Phase

End Right of Way Phase
01/18/2007 

01/24/2008 
10/15/2009 

10/15/2009 
07/01/2010 

09/30/2010 
100  05/12/2010 

10/27/2010 


-1 
Begin Construction Phase

End Construction Phase
05/12/2008 

05/30/2011 
10/15/2009 

10/15/2009 
05/31/2011 

05/31/2013 
100  05/20/2011 

04/08/2013 


Begin Closeout Phase

End Closeout Phase
09/30/2011 

 
 

 
11/30/2013 

 
100  04/09/2013 

11/06/2014 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$409,441
Current Approved:
$131,923
Actual Expenditures:
$131,923

 

Status as of December 31, 2023.